March 31, 2023

  • Box culvert was set March 16th.
  • Concrete wingwalls will be complete August 29th.
  • Backfill scheduled for the week of April 1st.
Share March 31, 2023 on Facebook Share March 31, 2023 on X (formerly Twitter) Share March 31, 2023 on Linkedin Email March 31, 2023 link

This project is substantially complete.