March 31, 2023
- Box culvert was set March 16th.
- Concrete wingwalls will be complete August 29th.
- Backfill scheduled for the week of April 1st.
Share March 31, 2023 on Facebook
Share March 31, 2023 on X (formerly Twitter)
Share March 31, 2023 on Linkedin
Email March 31, 2023 link
This project is substantially complete.