Black Cat Road Bridge

Share Black Cat Road Bridge on Facebook Share Black Cat Road Bridge on Twitter Share Black Cat Road Bridge on Linkedin Email Black Cat Road Bridge link

This project is substantially complete.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Black Cat Road, north of King Road, as early as the beginning of January 2023. Construction is expected to be complete spring of 2023.*

This bridge improvement project will include removing and replacing the existing bridge over the Benton Lateral.

*Due to high demand for contractors, labor and supplies, construction schedules may change.

Construction Impacts

  • Black Cat Road, just north of King Road, will be closed during construction
  • Lane restrictions
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to maintain access

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Black Cat Road, north of King Road, as early as the beginning of January 2023. Construction is expected to be complete spring of 2023.*

This bridge improvement project will include removing and replacing the existing bridge over the Benton Lateral.

*Due to high demand for contractors, labor and supplies, construction schedules may change.

Construction Impacts

  • Black Cat Road, just north of King Road, will be closed during construction
  • Lane restrictions
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to maintain access

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete.

  • February 17, 2023

    Share February 17, 2023 on Facebook Share February 17, 2023 on Twitter Share February 17, 2023 on Linkedin Email February 17, 2023 link
    • Irrigation boxes installed.
    • Bridge removed and excavated.
    • Prepping for headwalls.
    • Road removed.
  • February 10, 2023

    Share February 10, 2023 on Facebook Share February 10, 2023 on Twitter Share February 10, 2023 on Linkedin Email February 10, 2023 link
    • Waiting on irrigation structures.
    • Excavating for culvert.
    • Prepping for headwalls.
    • Road removed.
  • February 3, 2023

    Share February 3, 2023 on Facebook Share February 3, 2023 on Twitter Share February 3, 2023 on Linkedin Email February 3, 2023 link
    • Idaho Power is finishing relocating the poles.
    • Excavating for head walls starts February 2nd.
  • January 27, 2023

    Share January 27, 2023 on Facebook Share January 27, 2023 on Twitter Share January 27, 2023 on Linkedin Email January 27, 2023 link
    • Waiting on irrigation structures.
    • Road closed January 24th.
    • Idaho Power relocating power poles