  • Victory to Century Way - Paving complete. Finishing pavement markings night of August 13th & 14th.
  • Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain Starting Aug 10th. Electrical conduit being placed. Pole bases being placed.
  • Spectrum and Cole Intersection - Electrical work starting August 13th. Demo complete.