-
Share August 20, 2026 on Facebook
Share August 20, 2026 on X (formerly Twitter)
Share August 20, 2026 on Linkedin
Email August 20, 2026 link
Victory to Century Way - Complete.
Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical conduit being placed. Pole bases placed. Curb on-going. Utility in conflict with sidewalk.
Spectrum and Cole Intersection - Electrical work starting August 13th. Pole bases placed.
Victory to Century Way - Complete.
Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical conduit being placed. Pole bases placed. Curb on-going. Utility in conflict with sidewalk.
Spectrum and Cole Intersection - Electrical work starting August 13th. Pole bases placed.
-
Share August 14, 2026 on Facebook
Share August 14, 2026 on X (formerly Twitter)
Share August 14, 2026 on Linkedin
Email August 14, 2026 link
- Victory to Century Way - Paving complete. Finishing pavement markings night of August 13th & 14th.
- Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain Starting Aug 10th. Electrical conduit being placed. Pole bases being placed.
- Spectrum and Cole Intersection - Electrical work starting August 13th. Demo complete.
- Victory to Century Way - Paving complete. Finishing pavement markings night of August 13th & 14th.
- Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain Starting Aug 10th. Electrical conduit being placed. Pole bases being placed.
- Spectrum and Cole Intersection - Electrical work starting August 13th. Demo complete.
-
Share August 7, 2026 on Facebook
Share August 7, 2026 on X (formerly Twitter)
Share August 7, 2026 on Linkedin
Email August 7, 2026 link
- Victory to Century Way
- Paving complete
- Some pavement markings remaining
- Century Way and Cole Intersection
- Sidewalk removal starting July 30th
- Storm drain Starting Aug 10th
- Electrical conduit being placed
- Spectrum and Cole Intersection
- Electrical work starting August 13th
- Victory to Century Way
- Paving complete
- Some pavement markings remaining
- Century Way and Cole Intersection
- Sidewalk removal starting July 30th
- Storm drain Starting Aug 10th
- Electrical conduit being placed
- Spectrum and Cole Intersection
- Electrical work starting August 13th
-
Share July 30, 2026 on Facebook
Share July 30, 2026 on X (formerly Twitter)
Share July 30, 2026 on Linkedin
Email July 30, 2026 link
- Victory to Century Way - Paving Complete.
- Century Way and Cole Intersection - Starting at night July 29th. Sidewalk removal starting July 30th.
- Victory to Century Way - Paving Complete.
- Century Way and Cole Intersection - Starting at night July 29th. Sidewalk removal starting July 30th.
-
Share July 23, 2026 on Facebook
Share July 23, 2026 on X (formerly Twitter)
Share July 23, 2026 on Linkedin
Email July 23, 2026 link
- Victory to Century Way
- Paving approaches starting July 17th.
- Milling mainline starting July 20th at night.
- Paving mainline after the mill.
- Century Way and Cole Intersection - Starting July 28th.
- Victory to Century Way
- Paving approaches starting July 17th.
- Milling mainline starting July 20th at night.
- Paving mainline after the mill.
- Century Way and Cole Intersection - Starting July 28th.
-
Share July 17, 2026 on Facebook
Share July 17, 2026 on X (formerly Twitter)
Share July 17, 2026 on Linkedin
Email July 17, 2026 link
- Victory to Century Way
- Paving approaches starting July 17th
- Milling mainline starting July 20th at night
- Paving mainline after the mill
- Century Way and Cole Intersection
- Victory to Century Way
- Paving approaches starting July 17th
- Milling mainline starting July 20th at night
- Paving mainline after the mill
- Century Way and Cole Intersection
-
Share July 9, 2026 on Facebook
Share July 9, 2026 on X (formerly Twitter)
Share July 9, 2026 on Linkedin
Email July 9, 2026 link
Victory to Century Way
- Starting west side the week of June 15th.
- Removing concrete.
- Excavating for new sidewalk.
- Placing sidewalk.
- Paving approaches starting July 17th.
Victory to Century Way
- Starting west side the week of June 15th.
- Removing concrete.
- Excavating for new sidewalk.
- Placing sidewalk.
- Paving approaches starting July 17th.
-
Share July 1, 2026 on Facebook
Share July 1, 2026 on X (formerly Twitter)
Share July 1, 2026 on Linkedin
Email July 1, 2026 link
- Victory to Century Way
- Starting west side the week of June 15th.
- Removing concrete.
- Excavating for new sidewalk.
- Victory to Century Way
- Starting west side the week of June 15th.
- Removing concrete.
- Excavating for new sidewalk.
-
Share June 26, 2026 on Facebook
Share June 26, 2026 on X (formerly Twitter)
Share June 26, 2026 on Linkedin
Email June 26, 2026 link
Victory to Century Way
- Starting west side the week of June 15th.
- Removing concrete.
- Excavating for new sidewalk.
Victory to Century Way
- Starting west side the week of June 15th.
- Removing concrete.
- Excavating for new sidewalk.
-
Share June 18, 2026 on Facebook
Share June 18, 2026 on X (formerly Twitter)
Share June 18, 2026 on Linkedin
Email June 18, 2026 link
Victory to Century Way
- Starting west side the week of June 15th.
- Removing concrete.
- Excavating for a new sidewalk.
Victory to Century Way
- Starting west side the week of June 15th.
- Removing concrete.
- Excavating for a new sidewalk.