Cole Road, Victory Road to Overland Road
Starting as early as mid-April, the Ada County Highway District (ACHD) will begin reconstructing Cole Road from Victory Road to Overland Road. The pavement has reached the end of its service life and no longer meets current standards. Construction is expected to be complete in late fall 2026.*
Project Highlights
- Reconstructing the road surface on Cole Road from south of Overland Road to south of Mossy Cup Street, resulting in a new roadway surface throughout the corridor
- Upgrading existing pedestrian signals to Accessible Pedestrian Signals (APS) at the intersections of Cole Road and Entertainment Avenue, and Cole Road and Century Way
- Updating pedestrian ramps as needed to meet Americans with Disabilities Act (ADA) accessibility standards
Construction Impacts
- Night work is expected to help reduce daytime traffic impacts
- Lane restrictions with flaggers
- Pedestrian detours and sidewalk closures
- General construction impacts including noise, dust, equipment backup alarms, and ground vibration
- The contractor will work with property owners to minimize impacts
*Construction schedules may change.
Starting as early as mid-April, the Ada County Highway District (ACHD) will begin reconstructing Cole Road from Victory Road to Overland Road. The pavement has reached the end of its service life and no longer meets current standards. Construction is expected to be complete in late fall 2026.*
Project Highlights
- Reconstructing the road surface on Cole Road from south of Overland Road to south of Mossy Cup Street, resulting in a new roadway surface throughout the corridor
- Upgrading existing pedestrian signals to Accessible Pedestrian Signals (APS) at the intersections of Cole Road and Entertainment Avenue, and Cole Road and Century Way
- Updating pedestrian ramps as needed to meet Americans with Disabilities Act (ADA) accessibility standards
Construction Impacts
- Night work is expected to help reduce daytime traffic impacts
- Lane restrictions with flaggers
- Pedestrian detours and sidewalk closures
- General construction impacts including noise, dust, equipment backup alarms, and ground vibration
- The contractor will work with property owners to minimize impacts
*Construction schedules may change.
-
October 2, 2026
Share October 2, 2026 on Facebook Share October 2, 2026 on X (formerly Twitter) Share October 2, 2026 on Linkedin Email October 2, 2026 linkVictory to Century Way - Complete.
Century Way and Cole Intersection - Electrical complete. Pole bases complete. Curb and sidewalk ongoing. Paving anticipated the week of Oct 5th.
Spectrum and Cole Intersection - Pole bases placed. Concrete and curb ongoing. Paving anticipated the week of Oct 5th.
Victory to Century Way - Complete.
Century Way and Cole Intersection - Electrical complete. Pole bases complete. Curb and sidewalk ongoing. Paving anticipated the week of Oct 5th.
Spectrum and Cole Intersection - Pole bases placed. Concrete and curb ongoing. Paving anticipated the week of Oct 5th.
-
September 24, 2026
Share September 24, 2026 on Facebook Share September 24, 2026 on X (formerly Twitter) Share September 24, 2026 on Linkedin Email September 24, 2026 linkVictory to Century Way
- Complete
Century Way and Cole Intersection
- Electrical is complete.
- Pole bases are complete.
- Curb and sidewalk installation is ongoing.
- Paving anticipated the week of Oct 5th.
Spectrum and Cole Intersection
- Pole bases are placed.
- Concrete and curb installation is ongoing.
Victory to Century Way
- Complete
Century Way and Cole Intersection
- Electrical is complete.
- Pole bases are complete.
- Curb and sidewalk installation is ongoing.
- Paving anticipated the week of Oct 5th.
Spectrum and Cole Intersection
- Pole bases are placed.
- Concrete and curb installation is ongoing.
-
September 17, 2026
Share September 17, 2026 on Facebook Share September 17, 2026 on X (formerly Twitter) Share September 17, 2026 on Linkedin Email September 17, 2026 linkVictory to Century Way - Complete.
Century Way and Cole Intersection
- Sidewalk removal starting July 30th.
- Storm drain complete on west side.
- Electrical complete.
- Pole bases complete.
- Curb and sidewalk ongoing.
- Paving anticipated week of Oct 5th.
Spectrum and Cole Intersection
- Pole bases placed.
- Concrete and curb ongoing.
Victory to Century Way - Complete.
Century Way and Cole Intersection
- Sidewalk removal starting July 30th.
- Storm drain complete on west side.
- Electrical complete.
- Pole bases complete.
- Curb and sidewalk ongoing.
- Paving anticipated week of Oct 5th.
Spectrum and Cole Intersection
- Pole bases placed.
- Concrete and curb ongoing.
-
September 11, 2026
Share September 11, 2026 on Facebook Share September 11, 2026 on X (formerly Twitter) Share September 11, 2026 on Linkedin Email September 11, 2026 link- Victory to Century Way - Complete.
- Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical complete. Pole bases complete. Curb and sidewalk ongoing
- Spectrum and Cole Intersection - Pole bases placed.
- Victory to Century Way - Complete.
- Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical complete. Pole bases complete. Curb and sidewalk ongoing
- Spectrum and Cole Intersection - Pole bases placed.
-
September 3, 2026
Share September 3, 2026 on Facebook Share September 3, 2026 on X (formerly Twitter) Share September 3, 2026 on Linkedin Email September 3, 2026 link- Victory to Century Way - Complete.
- Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical complete. Pole bases complete. Curb on-going. Utility in conflict with sidewalk.
- Spectrum and Cole Intersection - Pole bases placed.
- Victory to Century Way - Complete.
- Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical complete. Pole bases complete. Curb on-going. Utility in conflict with sidewalk.
- Spectrum and Cole Intersection - Pole bases placed.
-
August 28, 2026
Share August 28, 2026 on Facebook Share August 28, 2026 on X (formerly Twitter) Share August 28, 2026 on Linkedin Email August 28, 2026 linkVictory to Century Way - Complete.
Century Way and Cole Intersection - Sidewalk removal started July 30th. Storm drain complete on west side. Electrical conduit being placed. Pole bases placed. Curb installation on-going. Utility in conflict with sidewalk.
Spectrum and Cole Intersection - Pole bases placed.
Victory to Century Way - Complete.
Century Way and Cole Intersection - Sidewalk removal started July 30th. Storm drain complete on west side. Electrical conduit being placed. Pole bases placed. Curb installation on-going. Utility in conflict with sidewalk.
Spectrum and Cole Intersection - Pole bases placed.
-
August 20, 2026
Share August 20, 2026 on Facebook Share August 20, 2026 on X (formerly Twitter) Share August 20, 2026 on Linkedin Email August 20, 2026 linkVictory to Century Way - Complete.
Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical conduit being placed. Pole bases placed. Curb on-going. Utility in conflict with sidewalk.
Spectrum and Cole Intersection - Electrical work starting August 13th. Pole bases placed.
Victory to Century Way - Complete.
Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical conduit being placed. Pole bases placed. Curb on-going. Utility in conflict with sidewalk.
Spectrum and Cole Intersection - Electrical work starting August 13th. Pole bases placed.
-
August 14, 2026
Share August 14, 2026 on Facebook Share August 14, 2026 on X (formerly Twitter) Share August 14, 2026 on Linkedin Email August 14, 2026 link- Victory to Century Way - Paving complete. Finishing pavement markings night of August 13th & 14th.
- Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain Starting Aug 10th. Electrical conduit being placed. Pole bases being placed.
- Spectrum and Cole Intersection - Electrical work starting August 13th. Demo complete.
- Victory to Century Way - Paving complete. Finishing pavement markings night of August 13th & 14th.
- Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain Starting Aug 10th. Electrical conduit being placed. Pole bases being placed.
- Spectrum and Cole Intersection - Electrical work starting August 13th. Demo complete.
-
August 7, 2026
Share August 7, 2026 on Facebook Share August 7, 2026 on X (formerly Twitter) Share August 7, 2026 on Linkedin Email August 7, 2026 link- Victory to Century Way
- Paving complete
- Some pavement markings remaining
- Century Way and Cole Intersection
- Sidewalk removal starting July 30th
- Storm drain Starting Aug 10th
- Electrical conduit being placed
- Spectrum and Cole Intersection
- Electrical work starting August 13th
- Victory to Century Way
- Paving complete
- Some pavement markings remaining
- Century Way and Cole Intersection
- Sidewalk removal starting July 30th
- Storm drain Starting Aug 10th
- Electrical conduit being placed
- Spectrum and Cole Intersection
- Electrical work starting August 13th
- Victory to Century Way
-
July 30, 2026
Share July 30, 2026 on Facebook Share July 30, 2026 on X (formerly Twitter) Share July 30, 2026 on Linkedin Email July 30, 2026 link- Victory to Century Way - Paving Complete.
- Century Way and Cole Intersection - Starting at night July 29th. Sidewalk removal starting July 30th.
- Victory to Century Way - Paving Complete.
- Century Way and Cole Intersection - Starting at night July 29th. Sidewalk removal starting July 30th.
-
Project Manager
Phone 208-387-6100 Email connect@achdidaho.org -
Community and Business Relations Coordinator
Phone 208-387-6100 Email connect@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email connect@achdidaho.org
-
2023/2024
Cole Road, Victory Road to Overland Road has finished this stageDesign
-
2024-2025
Cole Road, Victory Road to Overland Road has finished this stagePurchase property necessary for project.
-
2026
Cole Road, Victory Road to Overland Road is currently at this stageConstruction