Cole Road, Victory Road to Overland Road

Share Cole Road, Victory Road to Overland Road on Facebook Share Cole Road, Victory Road to Overland Road on Twitter Share Cole Road, Victory Road to Overland Road on Linkedin Email Cole Road, Victory Road to Overland Road link

Starting as early as mid-April, the Ada County Highway District (ACHD) will begin reconstructing Cole Road from Victory Road to Overland Road. The pavement has reached the end of its service life and no longer meets current standards. Construction is expected to be complete in late fall 2026.*

Project Highlights

  • Reconstructing the road surface on Cole Road from south of Overland Road to south of Mossy Cup Street, resulting in a new roadway surface throughout the corridor
  • Upgrading existing pedestrian signals to Accessible Pedestrian Signals (APS) at the intersections of Cole Road and Entertainment Avenue, and Cole Road and Century Way
  • Updating pedestrian ramps as needed to meet Americans with Disabilities Act (ADA) accessibility standards

Construction Impacts

  • Night work is expected to help reduce daytime traffic impacts
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
  • The contractor will work with property owners to minimize impacts

*Construction schedules may change.

Starting as early as mid-April, the Ada County Highway District (ACHD) will begin reconstructing Cole Road from Victory Road to Overland Road. The pavement has reached the end of its service life and no longer meets current standards. Construction is expected to be complete in late fall 2026.*

Project Highlights

  • Reconstructing the road surface on Cole Road from south of Overland Road to south of Mossy Cup Street, resulting in a new roadway surface throughout the corridor
  • Upgrading existing pedestrian signals to Accessible Pedestrian Signals (APS) at the intersections of Cole Road and Entertainment Avenue, and Cole Road and Century Way
  • Updating pedestrian ramps as needed to meet Americans with Disabilities Act (ADA) accessibility standards

Construction Impacts

  • Night work is expected to help reduce daytime traffic impacts
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
  • The contractor will work with property owners to minimize impacts

*Construction schedules may change.

  • Construction to Start Soon

    Share Construction to Start Soon on Facebook Share Construction to Start Soon on Twitter Share Construction to Start Soon on Linkedin Email Construction to Start Soon link

    Starting as early as mid-April, ACHD will begin reconstructing Cole Road from Victory Road to Overland Road. Construction is expected to be complete in late fall 2026.*

    Construction Impacts

    • Night work is expected to help reduce daytime traffic impacts
    • Lane restrictions with flaggers
    • Pedestrian detours and sidewalk closures
    • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
    • The contractor will work with property owners to minimize impacts

    *Construction schedules may change.

  • October 2, 2025

    Share October 2, 2025 on Facebook Share October 2, 2025 on Twitter Share October 2, 2025 on Linkedin Email October 2, 2025 link
    • Excavation and paving is complete.
    • Remaining work includes pavement markings. Work was scheduled for September 29th but delayed due to rain. Work has been rescheduled for October 7th.
    • Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
    • Work is weather-dependent.
  • September 26, 2025

    Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 link
    • Excavation and paving is complete.
    • Remaining work includes pavement markings. Work is scheduled for September 29th.
    • Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
    • Work is weather-dependent.
  • September 19, 2025

    Share September 19, 2025 on Facebook Share September 19, 2025 on Twitter Share September 19, 2025 on Linkedin Email September 19, 2025 link
    • Excavation and paving is complete.
    • Remaining work includes pavement markings.
    • Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
    • Work is weather-dependent.
  • September 12, 2025

    Share September 12, 2025 on Facebook Share September 12, 2025 on Twitter Share September 12, 2025 on Linkedin Email September 12, 2025 link

    Cole Road and Overland Road - Joint Repair

    • Contractor started on the east leg on September 7th.
    • Work will then proceed to the north and west legs.
    • Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
    • Work is weather-dependent.
  • September 5, 2025

    Share September 5, 2025 on Facebook Share September 5, 2025 on Twitter Share September 5, 2025 on Linkedin Email September 5, 2025 link
    • Contractor intends to start on the east leg on September 7th. Eastbound Overland Road will be restricted to one through lane; turn lanes will remain open.
  • April 15, 2025

    Share April 15, 2025 on Facebook Share April 15, 2025 on Twitter Share April 15, 2025 on Linkedin Email April 15, 2025 link
    • Project is currently in the Right of Way phase.
    • Notice to proceed date March 2026.
    • Cole Road Joint Repair - Notice to proceed date June 2025.
  • April 8, 2025

    Share April 8, 2025 on Facebook Share April 8, 2025 on Twitter Share April 8, 2025 on Linkedin Email April 8, 2025 link
    • Project is currently in the Right of Way phase.
    • Notice to proceed date for the project is March 2026.
Page last updated: 23 Mar 2026, 01:38 PM