Cole Road, Victory Road to Overland Road

Share Cole Road, Victory Road to Overland Road on Facebook Share Cole Road, Victory Road to Overland Road on X (formerly Twitter) Share Cole Road, Victory Road to Overland Road on Linkedin Email Cole Road, Victory Road to Overland Road link

Starting as early as mid-April, the Ada County Highway District (ACHD) will begin reconstructing Cole Road from Victory Road to Overland Road. The pavement has reached the end of its service life and no longer meets current standards. Construction is expected to be complete in late fall 2026.*

Project Highlights

  • Reconstructing the road surface on Cole Road from south of Overland Road to south of Mossy Cup Street, resulting in a new roadway surface throughout the corridor
  • Upgrading existing pedestrian signals to Accessible Pedestrian Signals (APS) at the intersections of Cole Road and Entertainment Avenue, and Cole Road and Century Way
  • Updating pedestrian ramps as needed to meet Americans with Disabilities Act (ADA) accessibility standards

Construction Impacts

  • Night work is expected to help reduce daytime traffic impacts
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
  • The contractor will work with property owners to minimize impacts

*Construction schedules may change.

Starting as early as mid-April, the Ada County Highway District (ACHD) will begin reconstructing Cole Road from Victory Road to Overland Road. The pavement has reached the end of its service life and no longer meets current standards. Construction is expected to be complete in late fall 2026.*

Project Highlights

  • Reconstructing the road surface on Cole Road from south of Overland Road to south of Mossy Cup Street, resulting in a new roadway surface throughout the corridor
  • Upgrading existing pedestrian signals to Accessible Pedestrian Signals (APS) at the intersections of Cole Road and Entertainment Avenue, and Cole Road and Century Way
  • Updating pedestrian ramps as needed to meet Americans with Disabilities Act (ADA) accessibility standards

Construction Impacts

  • Night work is expected to help reduce daytime traffic impacts
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
  • The contractor will work with property owners to minimize impacts

*Construction schedules may change.

  • October 22, 2026

    Share October 22, 2026 on Facebook Share October 22, 2026 on X (formerly Twitter) Share October 22, 2026 on Linkedin Email October 22, 2026 link

    Victory to Century Way - Complete.

    Century Way and Cole Intersection - West side paved. Landscaping remaining.

    Spectrum and Cole Intersection - Paved and open.

    Century way and Cole Intersection (East Side) - Work on the east side of the intersection started October 12th. Veolia working on pipe placement. Storm drain being installed.

    Victory to Century Way - Complete.

    Century Way and Cole Intersection - West side paved. Landscaping remaining.

    Spectrum and Cole Intersection - Paved and open.

    Century way and Cole Intersection (East Side) - Work on the east side of the intersection started October 12th. Veolia working on pipe placement. Storm drain being installed.

  • October 16, 2026

    Share October 16, 2026 on Facebook Share October 16, 2026 on X (formerly Twitter) Share October 16, 2026 on Linkedin Email October 16, 2026 link

    Victory to Century Way

    • Complete

    Century Way and Cole Intersection

    • West side paved.
    • Landscaping remaining.

    Spectrum and Cole Intersection

    • Paved and open

    Century way and Cole Intersection (East Side)

    • East side work of intersection anticipated starting October 12th.
    • Veolia working on place pipe.
    • Storm Drain being installed.

    Victory to Century Way

    • Complete

    Century Way and Cole Intersection

    • West side paved.
    • Landscaping remaining.

    Spectrum and Cole Intersection

    • Paved and open

    Century way and Cole Intersection (East Side)

    • East side work of intersection anticipated starting October 12th.
    • Veolia working on place pipe.
    • Storm Drain being installed.
  • October 9, 2026

    Share October 9, 2026 on Facebook Share October 9, 2026 on X (formerly Twitter) Share October 9, 2026 on Linkedin Email October 9, 2026 link

    Victory to Century Way - Complete.

    Century Way and Cole Intersection - Electrical complete. Pole bases complete. Curb and sidewalk installation ongoing. Paving anticipated the week of October 5th. Opening by October 9th.

    Spectrum and Cole Intersection - Pole bases placed. Concrete and curb installation ongoing. Paving anticipated the week of October 5th. Opening by Oct 9th.

    Century way and Cole Intersection (East Side) - East side work of intersection anticipated starting October 12th. Veolia working on placing pipe.

    Victory to Century Way - Complete.

    Century Way and Cole Intersection - Electrical complete. Pole bases complete. Curb and sidewalk installation ongoing. Paving anticipated the week of October 5th. Opening by October 9th.

    Spectrum and Cole Intersection - Pole bases placed. Concrete and curb installation ongoing. Paving anticipated the week of October 5th. Opening by Oct 9th.

    Century way and Cole Intersection (East Side) - East side work of intersection anticipated starting October 12th. Veolia working on placing pipe.

  • October 2, 2026

    Share October 2, 2026 on Facebook Share October 2, 2026 on X (formerly Twitter) Share October 2, 2026 on Linkedin Email October 2, 2026 link

    Victory to Century Way - Complete.

    Century Way and Cole Intersection - Electrical complete. Pole bases complete. Curb and sidewalk ongoing. Paving anticipated the week of Oct 5th.

    Spectrum and Cole Intersection - Pole bases placed. Concrete and curb ongoing. Paving anticipated the week of Oct 5th.

    Victory to Century Way - Complete.

    Century Way and Cole Intersection - Electrical complete. Pole bases complete. Curb and sidewalk ongoing. Paving anticipated the week of Oct 5th.

    Spectrum and Cole Intersection - Pole bases placed. Concrete and curb ongoing. Paving anticipated the week of Oct 5th.

  • September 24, 2026

    Share September 24, 2026 on Facebook Share September 24, 2026 on X (formerly Twitter) Share September 24, 2026 on Linkedin Email September 24, 2026 link

    Victory to Century Way

    • Complete

    Century Way and Cole Intersection

    • Electrical is complete.
    • Pole bases are complete.
    • Curb and sidewalk installation is ongoing.
    • Paving anticipated the week of Oct 5th.

    Spectrum and Cole Intersection

    • Pole bases are placed.
    • Concrete and curb installation is ongoing.


    Victory to Century Way

    • Complete

    Century Way and Cole Intersection

    • Electrical is complete.
    • Pole bases are complete.
    • Curb and sidewalk installation is ongoing.
    • Paving anticipated the week of Oct 5th.

    Spectrum and Cole Intersection

    • Pole bases are placed.
    • Concrete and curb installation is ongoing.


  • September 17, 2026

    Share September 17, 2026 on Facebook Share September 17, 2026 on X (formerly Twitter) Share September 17, 2026 on Linkedin Email September 17, 2026 link

    Victory to Century Way - Complete.

    Century Way and Cole Intersection

    • Sidewalk removal starting July 30th.
    • Storm drain complete on west side.
    • Electrical complete.
    • Pole bases complete.
    • Curb and sidewalk ongoing.
    • Paving anticipated week of Oct 5th.

    Spectrum and Cole Intersection

    • Pole bases placed.
    • Concrete and curb ongoing.


    Victory to Century Way - Complete.

    Century Way and Cole Intersection

    • Sidewalk removal starting July 30th.
    • Storm drain complete on west side.
    • Electrical complete.
    • Pole bases complete.
    • Curb and sidewalk ongoing.
    • Paving anticipated week of Oct 5th.

    Spectrum and Cole Intersection

    • Pole bases placed.
    • Concrete and curb ongoing.


  • September 11, 2026

    Share September 11, 2026 on Facebook Share September 11, 2026 on X (formerly Twitter) Share September 11, 2026 on Linkedin Email September 11, 2026 link
    • Victory to Century Way - Complete.
    • Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical complete. Pole bases complete. Curb and sidewalk ongoing
    • Spectrum and Cole Intersection - Pole bases placed.
    • Victory to Century Way - Complete.
    • Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical complete. Pole bases complete. Curb and sidewalk ongoing
    • Spectrum and Cole Intersection - Pole bases placed.
  • September 3, 2026

    Share September 3, 2026 on Facebook Share September 3, 2026 on X (formerly Twitter) Share September 3, 2026 on Linkedin Email September 3, 2026 link
    • Victory to Century Way - Complete.
    • Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical complete. Pole bases complete. Curb on-going. Utility in conflict with sidewalk.
    • Spectrum and Cole Intersection - Pole bases placed.
    • Victory to Century Way - Complete.
    • Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical complete. Pole bases complete. Curb on-going. Utility in conflict with sidewalk.
    • Spectrum and Cole Intersection - Pole bases placed.
  • August 28, 2026

    Share August 28, 2026 on Facebook Share August 28, 2026 on X (formerly Twitter) Share August 28, 2026 on Linkedin Email August 28, 2026 link

    Victory to Century Way - Complete.

    Century Way and Cole Intersection - Sidewalk removal started July 30th. Storm drain complete on west side. Electrical conduit being placed. Pole bases placed. Curb installation on-going. Utility in conflict with sidewalk.

    Spectrum and Cole Intersection - Pole bases placed.

    Victory to Century Way - Complete.

    Century Way and Cole Intersection - Sidewalk removal started July 30th. Storm drain complete on west side. Electrical conduit being placed. Pole bases placed. Curb installation on-going. Utility in conflict with sidewalk.

    Spectrum and Cole Intersection - Pole bases placed.

  • August 20, 2026

    Share August 20, 2026 on Facebook Share August 20, 2026 on X (formerly Twitter) Share August 20, 2026 on Linkedin Email August 20, 2026 link

    Victory to Century Way - Complete.

    Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical conduit being placed. Pole bases placed. Curb on-going. Utility in conflict with sidewalk.

    Spectrum and Cole Intersection - Electrical work starting August 13th. Pole bases placed.

    Victory to Century Way - Complete.

    Century Way and Cole Intersection - Sidewalk removal starting July 30th. Storm drain complete on west side. Electrical conduit being placed. Pole bases placed. Curb on-going. Utility in conflict with sidewalk.

    Spectrum and Cole Intersection - Electrical work starting August 13th. Pole bases placed.

Page last updated: 22 Oct 2026, 07:53 PM