Cole Road, Victory Road to Overland Road

Share Cole Road, Victory Road to Overland Road on Facebook Share Cole Road, Victory Road to Overland Road on Twitter Share Cole Road, Victory Road to Overland Road on Linkedin Email Cole Road, Victory Road to Overland Road link

Starting as early as mid-April, the Ada County Highway District (ACHD) will begin reconstructing Cole Road from Victory Road to Overland Road. The pavement has reached the end of its service life and no longer meets current standards. Construction is expected to be complete in late fall 2026.*

Project Highlights

  • Reconstructing the road surface on Cole Road from south of Overland Road to south of Mossy Cup Street, resulting in a new roadway surface throughout the corridor
  • Upgrading existing pedestrian signals to Accessible Pedestrian Signals (APS) at the intersections of Cole Road and Entertainment Avenue, and Cole Road and Century Way
  • Updating pedestrian ramps as needed to meet Americans with Disabilities Act (ADA) accessibility standards

Construction Impacts

  • Night work is expected to help reduce daytime traffic impacts
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
  • The contractor will work with property owners to minimize impacts

*Construction schedules may change.

Starting as early as mid-April, the Ada County Highway District (ACHD) will begin reconstructing Cole Road from Victory Road to Overland Road. The pavement has reached the end of its service life and no longer meets current standards. Construction is expected to be complete in late fall 2026.*

Project Highlights

  • Reconstructing the road surface on Cole Road from south of Overland Road to south of Mossy Cup Street, resulting in a new roadway surface throughout the corridor
  • Upgrading existing pedestrian signals to Accessible Pedestrian Signals (APS) at the intersections of Cole Road and Entertainment Avenue, and Cole Road and Century Way
  • Updating pedestrian ramps as needed to meet Americans with Disabilities Act (ADA) accessibility standards

Construction Impacts

  • Night work is expected to help reduce daytime traffic impacts
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
  • The contractor will work with property owners to minimize impacts

*Construction schedules may change.

  • June 18, 2026

    Share June 18, 2026 on Facebook Share June 18, 2026 on Twitter Share June 18, 2026 on Linkedin Email June 18, 2026 link

    Victory to Century Way

    • Starting west side the week of June 15th.
    • Removing concrete.
    • Excavating for a new sidewalk.

    Victory to Century Way

    • Starting west side the week of June 15th.
    • Removing concrete.
    • Excavating for a new sidewalk.
  • June 12, 2026

    Share June 12, 2026 on Facebook Share June 12, 2026 on Twitter Share June 12, 2026 on Linkedin Email June 12, 2026 link

    Victory to Century Way

    • Started May 7th.
    • Removing and replacing sidewalk on the east side.
    • Paving June 13th.
    • Switching traffic to work on west side on June 13th.
    • Starting west side week of June 15th.

    Victory to Century Way

    • Started May 7th.
    • Removing and replacing sidewalk on the east side.
    • Paving June 13th.
    • Switching traffic to work on west side on June 13th.
    • Starting west side week of June 15th.
  • June 5, 2026

    Share June 5, 2026 on Facebook Share June 5, 2026 on Twitter Share June 5, 2026 on Linkedin Email June 5, 2026 link

    Victory and Century Way

    • Started May 7th.
    • Removing and replacing sidewalk on the east side.
    • Starting west side week of June 8th.

    Victory and Century Way

    • Started May 7th.
    • Removing and replacing sidewalk on the east side.
    • Starting west side week of June 8th.
  • May 29, 2026

    Share May 29, 2026 on Facebook Share May 29, 2026 on Twitter Share May 29, 2026 on Linkedin Email May 29, 2026 link

    Victory and Century Way

    • Started May 7th.
    • Removing and replacing sidewalk on the east side.
    • Starting west side week of June 8th.

    Victory and Century Way

    • Started May 7th.
    • Removing and replacing sidewalk on the east side.
    • Starting west side week of June 8th.
  • May 21, 2026

    Share May 21, 2026 on Facebook Share May 21, 2026 on Twitter Share May 21, 2026 on Linkedin Email May 21, 2026 link

    Victory and Century Way

    • Started May 7th.
    • Removing and replacing sidewalk on the west side.
    • Starting east side May 27th.

    Victory and Century Way

    • Started May 7th.
    • Removing and replacing sidewalk on the west side.
    • Starting east side May 27th.
  • May 13, 2026

    Share May 13, 2026 on Facebook Share May 13, 2026 on Twitter Share May 13, 2026 on Linkedin Email May 13, 2026 link
    • Victory and Century Way - Started May 7th. Removing and replacing sidewalk.
    • Victory and Century Way - Started May 7th. Removing and replacing sidewalk.
  • May 8, 2026

    Share May 8, 2026 on Facebook Share May 8, 2026 on Twitter Share May 8, 2026 on Linkedin Email May 8, 2026 link
    • Victory and Century Way - Starting May 7th.
      • Removing and replacing sidewalk.
    • Victory and Century Way - Starting May 7th.
      • Removing and replacing sidewalk.
  • Construction to Start Soon

    Share Construction to Start Soon on Facebook Share Construction to Start Soon on Twitter Share Construction to Start Soon on Linkedin Email Construction to Start Soon link

    Starting as early as mid-April, ACHD will begin reconstructing Cole Road from Victory Road to Overland Road. Construction is expected to be complete in late fall 2026.*

    Construction Impacts

    • Night work is expected to help reduce daytime traffic impacts
    • Lane restrictions with flaggers
    • Pedestrian detours and sidewalk closures
    • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
    • The contractor will work with property owners to minimize impacts

    *Construction schedules may change.

    Starting as early as mid-April, ACHD will begin reconstructing Cole Road from Victory Road to Overland Road. Construction is expected to be complete in late fall 2026.*

    Construction Impacts

    • Night work is expected to help reduce daytime traffic impacts
    • Lane restrictions with flaggers
    • Pedestrian detours and sidewalk closures
    • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
    • The contractor will work with property owners to minimize impacts

    *Construction schedules may change.

  • October 2, 2025

    Share October 2, 2025 on Facebook Share October 2, 2025 on Twitter Share October 2, 2025 on Linkedin Email October 2, 2025 link
    • Excavation and paving is complete.
    • Remaining work includes pavement markings. Work was scheduled for September 29th but delayed due to rain. Work has been rescheduled for October 7th.
    • Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
    • Work is weather-dependent.
    • Excavation and paving is complete.
    • Remaining work includes pavement markings. Work was scheduled for September 29th but delayed due to rain. Work has been rescheduled for October 7th.
    • Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
    • Work is weather-dependent.
  • September 26, 2025

    Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 link
    • Excavation and paving is complete.
    • Remaining work includes pavement markings. Work is scheduled for September 29th.
    • Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
    • Work is weather-dependent.
    • Excavation and paving is complete.
    • Remaining work includes pavement markings. Work is scheduled for September 29th.
    • Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
    • Work is weather-dependent.
Page last updated: 18 Jun 2026, 09:26 AM