November 13, 2026

Century way and Cole Intersection (East Side)

  • Work on the east side of the intersection started October 12th.
  • Veolia working on replacing water from S. Century way to Spectrum.
  • Retaining wall ongoing.
  • New traffic pattern was implemented November 6th.