October 9, 2026
Victory to Century Way - Complete.
Century Way and Cole Intersection - Electrical complete. Pole bases complete. Curb and sidewalk installation ongoing. Paving anticipated the week of October 5th. Opening by October 9th.
Spectrum and Cole Intersection - Pole bases placed. Concrete and curb installation ongoing. Paving anticipated the week of October 5th. Opening by Oct 9th.
Century way and Cole Intersection (East Side) - East side work of intersection anticipated starting October 12th. Veolia working on placing pipe.