October 9, 2026

Victory to Century Way - Complete.

Century Way and Cole Intersection - Electrical complete. Pole bases complete. Curb and sidewalk installation ongoing. Paving anticipated the week of October 5th. Opening by October 9th.

Spectrum and Cole Intersection - Pole bases placed. Concrete and curb installation ongoing. Paving anticipated the week of October 5th. Opening by Oct 9th.

Century way and Cole Intersection (East Side) - East side work of intersection anticipated starting October 12th. Veolia working on placing pipe.

Share October 9, 2026 on Facebook Share October 9, 2026 on X (formerly Twitter) Share October 9, 2026 on Linkedin Email October 9, 2026 link