January 5, 2024
- Columba road closed for the duration of the project.
- Prepping trench for placing culvert.
- Placing culvert.
- Footings and wingwalls after culvert placed.
Share January 5, 2024 on Facebook
Share January 5, 2024 on Twitter
Share January 5, 2024 on Linkedin
Email January 5, 2024 link
This project is substantially complete.