February 10, 2023

  • Work continues on the south side of Cory.
  • One-way traffic set for vehicles to travel west only, between Maple Grove and Mitchell.
  • Pipe work has started.
  • Contractor has procured precast sections.
  • Utility work continues.
  • Integrity was on site to investigate the pipe.
Share February 10, 2023 on Facebook Share February 10, 2023 on Twitter Share February 10, 2023 on Linkedin Email February 10, 2023 link

This project is substantially complete.