February 17, 2023
- Work continues on south side of Cory.
- One way traffic set for vehicles to travel west only, between Maple Grove and Mitchell.
- Pipe work has started.
- Contractor will have to CIPP line existing irrigation pipe (roughly 50ft) to avoid communication box conflict.
- Utility work continues.
- Tree removal scheduled for this week and next.
Share February 17, 2023 on Facebook
Share February 17, 2023 on Twitter
Share February 17, 2023 on Linkedin
Email February 17, 2023 link
This project is substantially complete.