February 24, 2023

  • Work continues on the south side of Cory.
  • One-way traffic set for vehicles to ravel west only, between Maple Grove and Mitchell.
  • Pipe work has started - contractor will have to CIPP line existing irrigation pipe (roughly 50ft) to avoid communication box conflict.
  • Utility work continues.
  • Tree removal complete.
  • Pipe work and seepage bed at the corner of Cory and Dalton nearly complete.
Share February 24, 2023 on Facebook Share February 24, 2023 on X (formerly Twitter) Share February 24, 2023 on Linkedin Email February 24, 2023 link

This project is substantially complete.