- Work continues on the south side of Cory.
- One-way traffic set for vehicles to ravel west only, between Maple Grove and Mitchell.
- Pipe work has started - contractor will have to CIPP line existing irrigation pipe (roughly 50ft) to avoid communication box conflict.
- Utility work continues.
- Tree removal complete.
- Pipe work and seepage bed at the corner of Cory and Dalton nearly complete.
Share February 24, 2023 on Facebook
Share February 24, 2023 on X (formerly Twitter)
Share February 24, 2023 on Linkedin
Email February 24, 2023 link
This project is substantially complete.