March 17, 2023
- Work continues on the south side of Cory.
- One-way traffic set for vehicles to travel west only between Maple Grove and Mitchell.
- Pipe work continues - CIPP complete on south side of Cory.
- Utility work continues.
- Work on the SW side of Cory, near Mitchell continues.
- Maple Grove irrigation crossing started. Contractor expects it to be complete by March 17th.
Share March 17, 2023 on Facebook
Share March 17, 2023 on X (formerly Twitter)
Share March 17, 2023 on Linkedin
Email March 17, 2023 link
This project is substantially complete.