March 24, 2023
- Work continues on the south side of Cory.
- One way traffic set for vehicles to travel west only between Maple Grove and Mitchell.
- Pipe work complete.
- Utility work ongoing.
- Concrete on Cory is ongoing.
Share March 24, 2023 on Facebook
Share March 24, 2023 on Twitter
Share March 24, 2023 on Linkedin
Email March 24, 2023 link
This project is substantially complete.