March 3, 2023

  • Work continues on the south side of Cory.
  • One way traffic set for vehicles to travel west only between Maple Grove and Mitchell.
  • Pipe work continues. Contractor will have to CIPP line existing irrigation pipe (roughly 50 ft) to avoid communication box conflict.
  • Utility work continues.
  • Tree removal complete on the south side of the project.
  • Pipe work and seepage bed at the east corner of Cory and Dalton complete. West side work continues.
  • Linda Vista closure starting Monday, March 6 for irrigation work.
Share March 3, 2023 on Facebook Share March 3, 2023 on X (formerly Twitter) Share March 3, 2023 on Linkedin Email March 3, 2023 link

This project is substantially complete.