March 3, 2023

  • Work continues on the south side of Cory.
  • One way traffic set for vehicles to travel west only between Maple Grove and Mitchell.
  • Pipe work continues. Contractor will have to CIPP line existing irrigation pipe (roughly 50 ft) to avoid communication box conflict.
  • Utility work continues.
  • Tree removal complete on the south side of the project.
  • Pipe work and seepage bed at the east corner of Cory and Dalton complete. West side work continues.
  • Linda Vista closure starting Monday, March 6 for irrigation work.
Share March 3, 2023 on Facebook Share March 3, 2023 on Twitter Share March 3, 2023 on Linkedin Email March 3, 2023 link

This project is substantially complete.

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>