March 3, 2023
- Work continues on the south side of Cory.
- One way traffic set for vehicles to travel west only between Maple Grove and Mitchell.
- Pipe work continues. Contractor will have to CIPP line existing irrigation pipe (roughly 50 ft) to avoid communication box conflict.
- Utility work continues.
- Tree removal complete on the south side of the project.
- Pipe work and seepage bed at the east corner of Cory and Dalton complete. West side work continues.
- Linda Vista closure starting Monday, March 6 for irrigation work.
Share March 3, 2023 on Facebook
Share March 3, 2023 on X (formerly Twitter)
Share March 3, 2023 on Linkedin
Email March 3, 2023 link
This project is substantially complete.