March 31, 2023

  • Work continues on south side of Cory.
  • One-way traffic set for vehicles to travel west only, between Maple Grove and Mitchell.
  • Pipe work complete across Maple Grove.
  • Irrigation box set at Linda Vista - minor rework to accommodate development.
  • Utility work ongoing.
  • Concrete work on Cory is ongoing.
Share March 31, 2023 on Facebook Share March 31, 2023 on Twitter Share March 31, 2023 on Linkedin Email March 31, 2023 link

This project is substantially complete.