Construction Mid January - Early Summer 2023*

The Ada County Highway District (ACHD) will start construction on Cory Lane between Mitchell Street and Maple Grove Road, as early as mid-January 2023. The purpose of this project is to improve safety and increase connectivity for pedestrians. Construction is anticipated to be completed in the early summer of 2023.*

Project Description

  • Fill sidewalk gaps along both sides of the roadway between Mitchell Street and Maple Grove Road
  • Install bulb-outs at select locations to increase pedestrian safety and calm traffic
  • Upgrade pedestrian ramps to current standards
  • Upgrade storm drainage facilities
  • Relocate irrigation facilities to facilitate pedestrian improvements

*Due to high demand for contractors, labor and supplies, construction schedules may change.

Construction Impacts

  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize impacts

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

Construction Mid January - Early Summer 2023*

The Ada County Highway District (ACHD) will start construction on Cory Lane between Mitchell Street and Maple Grove Road, as early as mid-January 2023. The purpose of this project is to improve safety and increase connectivity for pedestrians. Construction is anticipated to be completed in the early summer of 2023.*

Project Description

  • Fill sidewalk gaps along both sides of the roadway between Mitchell Street and Maple Grove Road
  • Install bulb-outs at select locations to increase pedestrian safety and calm traffic
  • Upgrade pedestrian ramps to current standards
  • Upgrade storm drainage facilities
  • Relocate irrigation facilities to facilitate pedestrian improvements

*Due to high demand for contractors, labor and supplies, construction schedules may change.

Construction Impacts

  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize impacts

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete.

  • June 16, 2023

    Share June 16, 2023 on Facebook Share June 16, 2023 on Twitter Share June 16, 2023 on Linkedin Email June 16, 2023 link
    • Work continues on the north side of Cory.
    • One way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
    • Water work ongoing on north side of the road.
    • Concrete demo continues.
    • Grade prep and concrete work ongoing.
  • June 2, 2023

    Share June 2, 2023 on Facebook Share June 2, 2023 on Twitter Share June 2, 2023 on Linkedin Email June 2, 2023 link
    • Work continues on the north side of Cory.
    • One way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
    • Water work started on north side of the road.
    • Concrete demo continues.
  • May 26, 2023

    Share May 26, 2023 on Facebook Share May 26, 2023 on Twitter Share May 26, 2023 on Linkedin Email May 26, 2023 link
    • Work started on the north side of Cory.
    • One way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
    • Water work started on the north side of the road. Concrete demo started.
  • May 19, 2023

    Share May 19, 2023 on Facebook Share May 19, 2023 on Twitter Share May 19, 2023 on Linkedin Email May 19, 2023 link
    • Work continues on the south side of Cory.
    • One way traffic set for vehicles to travel west only, between Maple Grove and Mitchell.
    • Minor utility work remains.
    • Concrete work on Cory Lane - ongoing.
  • May 12, 2023

    Share May 12, 2023 on Facebook Share May 12, 2023 on Twitter Share May 12, 2023 on Linkedin Email May 12, 2023 link
    • Work continues on the south side of Cory.
    • One-way traffic set for vehicles to travel west only, between Maple Grove and Mitchell.
    • Utility work on-going.
    • Concrete work on Cory is on-going.
  • May 5, 2023

    Share May 5, 2023 on Facebook Share May 5, 2023 on Twitter Share May 5, 2023 on Linkedin Email May 5, 2023 link
    • Work continues on the south side of Cory.
    • One-way traffic set for vehicles to travel west only, between Maple Grove and Mitchell.
    • Utility work ongoing.
    • Concrete work on Cory is ongoing.
  • April 21, 2023

    Share April 21, 2023 on Facebook Share April 21, 2023 on Twitter Share April 21, 2023 on Linkedin Email April 21, 2023 link
    • Work continues on the south side of Cory.
    • One way traffic set for vehicles to travel west only between Maple Grove and Mitchell.
    • Utility work ongoing.
    • Concrete work on Cory is ongoing.
  • April 14, 2023

    Share April 14, 2023 on Facebook Share April 14, 2023 on Twitter Share April 14, 2023 on Linkedin Email April 14, 2023 link
    • Work continues on the south side of Cory between Maple Grove and Mitchell.
    • One-way traffic set for vehicles to travel west.
    • Utility work ongoing.
    • Concrete work on Cory is ongoing.
  • April 7, 2023

    Share April 7, 2023 on Facebook Share April 7, 2023 on Twitter Share April 7, 2023 on Linkedin Email April 7, 2023 link
    • Work continues on the south side of Cory.
    • One-way traffic set for vehicles to travel west between Maple Grove and Mitchell.
    • Utility work ongoing.
    • Concrete work on Cory is ongoing.
  • March 31, 2023

    Share March 31, 2023 on Facebook Share March 31, 2023 on Twitter Share March 31, 2023 on Linkedin Email March 31, 2023 link
    • Work continues on south side of Cory.
    • One-way traffic set for vehicles to travel west only, between Maple Grove and Mitchell.
    • Pipe work complete across Maple Grove.
    • Irrigation box set at Linda Vista - minor rework to accommodate development.
    • Utility work ongoing.