April 12, 2024 - Construction Update

Phase 1

  • Northeast corner of Eagle and Plaza
    • Utilities relocating.
    • Signal work ongoing.
    • Landscaping wall ongoing.
  • Plaza and Eagle Closure
    • Closed from April 1st – 15th.
    • Veolia tie in water in middle of intersection then proceeding down Plaza.
    • Signal work crossing Eagle Road.
    • Irrigation and conduits crossing Eagle during closure.
  • Eagle Closure - April 15th - April 30th between Plaza and Aikens
    • Bore under canal starting April 10th.
    • Veolia water line to Aikens.
Share April 12, 2024 - Construction Update on Facebook Share April 12, 2024 - Construction Update on Twitter Share April 12, 2024 - Construction Update on Linkedin Email April 12, 2024 - Construction Update link