Phase 1
-
Northeast corner of Eagle and Plaza
- Utilities relocating.
- Signal work ongoing.
- Landscaping wall ongoing.
- Plaza and Eagle Closure
- Closed from April 1st – 15th.
- Veolia tie in water in middle of intersection then proceeding down Plaza.
- Signal work crossing Eagle Road.
- Irrigation and conduits crossing Eagle during closure.
-
Eagle Closure - April 15th - April 30th between Plaza and Aikens
- Bore under canal starting April 10th.
- Veolia water line to Aikens.