Downtown Eagle Mobility Improvements: Eagle Road and State Street
The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.
The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.
Goals
The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.
The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.
The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.
Goals
The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.
-
May 8, 2025
08 May 2025Share May 8, 2025 on Facebook Share May 8, 2025 on Twitter Share May 8, 2025 on Linkedin Email May 8, 2025 linkOlde Park Place
- Landscape ongoing.
- Brick pavers installation.
Aikens between 2nd and Eagle
- Placing silva cells.
- Placing ¾” aggregate for road base.
- Electrical work ongoing.
- Curb anticipated week of May 5th.
Olde Park to Eagle Rd
- Road closure anticipated May 5th – end of May.
- Veolia installing water.
- Silva cells ongoing.
- Prepping and placing sidewalk crossings.
-
May 1, 2025
01 May 2025Share May 1, 2025 on Facebook Share May 1, 2025 on Twitter Share May 1, 2025 on Linkedin Email May 1, 2025 linkOlde Park
- Landscape ongoing
Aikens between 2nd and Eagle
- Placing Silva Cells
- Placing ¾” aggregate for road base
- Electrical work ongoing
- Curb anticipated week of May 5th
Olde Park To Eagle Rd
- Road closure anticipated May 5th – May 30th
- Veolia installing water
- Silva cells ongoing
- Prepping and placing sidewalk crossings
-
May 1, 2025 - New Detour Map & Information
01 May 2025Share May 1, 2025 - New Detour Map & Information on Facebook Share May 1, 2025 - New Detour Map & Information on Twitter Share May 1, 2025 - New Detour Map & Information on Linkedin Email May 1, 2025 - New Detour Map & Information linkState (Old State) between Olde Park Place and Eagle Road will be closed from
May 5th through the end of May.
-
April 25, 2025
25 Apr 2025Share April 25, 2025 on Facebook Share April 25, 2025 on Twitter Share April 25, 2025 on Linkedin Email April 25, 2025 linkVeolia
- Working at the intersection of Olde Park and State Street
- Lane shifts to install crossings
- Started Aikens and 2nd on March 31st - Complete.
Olde Park
- Paving complete.
- Concrete collars and pavement markings ongoing.
- Landscape ongoing.
Aikens between 2nd and Eagle
- Placing Silva Cells.
- Placing ¾” aggregate for road base.
- Storm drain and irrigation complete.
- Electrical work ongoing.
Olde Park To Eagle Rd on State (Old State)
- Road closure anticipated second week of May through end of May.
-
April 17, 2025
17 Apr 2025Share April 17, 2025 on Facebook Share April 17, 2025 on Twitter Share April 17, 2025 on Linkedin Email April 17, 2025 linkVeolia
- Working at the intersection of Olde Park and State Street.
- Lane shifts to install crossings.
- Starting Aikens and 2nd on March 31st - Complete.
Olde Park
- Silva Cells ongoing.
- Electrical and landscaping ongoing.
- Working in State Street on Silva Cells.
- Curb and gutter ongoing.
- Paving anticipated the week of April 21st.
- Pavement markings after paving.
Aikens between 2nd and Eagle
- Sub grading road.
- Placing Silva Cells.
- Storm drain and irrigation ongoing.
- Electrical work ongoing.
-
April 11, 2025
11 Apr 2025Share April 11, 2025 on Facebook Share April 11, 2025 on Twitter Share April 11, 2025 on Linkedin Email April 11, 2025 linkVeolia
- Working at the intersection of Olde Park and State Street.
- Lane shifts to install crossings.
- Starting Aikens and 2nd on March 31st - Complete.
Olde Park
- Silva Cells ongoing.
- Electrical and landscaping ongoing.
- Working in State Street on Silva Cells.
- Curb and gutter ongoing.
- Paving anticipated the week of April 14th.
- Pavement markings.
Aikens between 2nd and Eagle
- Sub grading road.
- Placing Silva Cells.
- Storm drain and irrigation ongoing.
- Electrical work ongoing.
-
April 4, 2025
04 Apr 2025Share April 4, 2025 on Facebook Share April 4, 2025 on Twitter Share April 4, 2025 on Linkedin Email April 4, 2025 linkVeolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.TBD.
- Starting Aikens and 2nd on March 31 - ongoing.
Olde Park
- Silva cells ongoing.
- Electrical and landscaping ongoing.
- Working in State Street working on Silva Cells.
- Placing structural fill.
- Curb and gutter ongoing.
Aikens between 2nd and Eagle
- Sub grading road.
- Placing silva cells.
- Storm drain and irrigation.
-
March 28, 2025
28 Mar 2025Share March 28, 2025 on Facebook Share March 28, 2025 on Twitter Share March 28, 2025 on Linkedin Email March 28, 2025 linkEagle Road in front of Albertsons
- Culvert complete.
- Retaining wall ongoing.
- Paving complete.
- Pavement markings complete.
- Swale ongoing.
- Minor items remaining.
Veolia
- Working at the intersection of Olde Park and State Street
- Night work 8pm – 7am - TBD
- Starting on Aikens between 2nd and Eagle.
Olde Park Place
- Storm Drain and irrigation complete.
- Excavation and backfill ongoing. Electrical and landscaping ongoing.
- Working in State Street working on Silva Cells.
- Placing structural fill.
- Curb and gutter starting first week of April.
Aikens between 2nd and Eagle
- Eagle Sewer is complete.
- Sub grading road.
-
March 20, 2024
20 Mar 2025Share March 20, 2024 on Facebook Share March 20, 2024 on Twitter Share March 20, 2024 on Linkedin Email March 20, 2024 linkEagle Road in front of Albertsons
- Culvert complete.
- Retaining wall ongoing.
- Curb and gutter getting placed.
- Swale ongoing.
- Paving anticipated March 21st.
- Concrete median anticipated start March 24th.
Veolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am - Pending Veolia’s contractor schedule.
Olde Park
- Storm drain and irrigation complete.
- Excavation and backfill ongoing.
- Electrical and landscaping ongoing.
- Working in State Street working on Silva Cells.
Aikens between 2nd and Eagle
- Waiting for Eagle Sewer’s contractor to be complete.
-
March 14, 2025
14 Mar 2025Share March 14, 2025 on Facebook Share March 14, 2025 on Twitter Share March 14, 2025 on Linkedin Email March 14, 2025 linkEagle Road in front of Albertsons
- Culvert complete
- Retaining wall ongoing
- Curb and gutter getting placed
- Swale ongoing
- Approach at Albertsons ongoing
Veolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.
Olde Park Place
- Storm Drain and Irrigation complete
- Excavation and backfill ongoing
- Electrical and landscaping ongoing
- Working in State Street working on Silva Cells
Related projects
Live Projects
Materials from Phase 2 Construction Open House
Construction Open House
-
January 23 2025
-
January 31 2024
Monthly Public Pop Up
-
August 29 2024
-
July 20 2024
-
June 27 2024
-
May 30 2024
-
April 25 2024
Drone Footage
-
May 06 2025
-
April 21 2025
-
April 04 2025
-
March 11 2025
-
November 13 2024
Materials from Construction Open House
Follow Project
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email projects@achdidaho.org (External link) -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org (External link) -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org (External link)
History
The design was the outcome of the Eagle Road and States Street Concept Design, an effort that began in 2012. After working with the community and the City of Eagle to evaluate multiple alternatives, the ACHD Commission approved the City's request to design and construct the Quadrant Alternative. This alternative best balances the need to safely accommodate the expected traffic growth, minimize impacts to adjacent properties and parking, and make downtown Eagle more walkable and bikeable, as well as being respectful of downtown's history and small town feel.