Share December 20, 2024 on Facebook
Share December 20, 2024 on Linkedin
Email December 20, 2024 link
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
Share December 12, 2024 on Facebook
Share December 12, 2024 on Linkedin
Email December 12, 2024 link
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
Share December 6, 2024 on Facebook
Share December 6, 2024 on Linkedin
Email December 6, 2024 link
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
Share November 22, 2024 on Facebook
Share November 22, 2024 on Linkedin
Email November 22, 2024 link
Eagle Road in front of Albertsons
- Power pole areas repaired and paved.
- Swale ongoing.
2nd Street and State Street
- Crosswalks being installed.
- Pavers being installed.
- Signal turn on anticipated November 21st.
Share November 15, 2024 on Facebook
Share November 15, 2024 on Linkedin
Email November 15, 2024 link
Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.
Share November 7, 2024 on Facebook
Share November 7, 2024 on Linkedin
Email November 7, 2024 link
Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.
Share November 1, 2024 on Facebook
Share November 1, 2024 on Linkedin
Email November 1, 2024 link
Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open - moving back over to finish Eagle Rd.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- Asphalt complete.
Share October 24, 2024 on Facebook
Share October 24, 2024 on Linkedin
Email October 24, 2024 link
Eagle Road in front of Albertsons
- Idaho Power relocating poles
2nd Street and State Street
- 2nd and State intersection closed.
- Silva Cells installed.
- Light pole bases, conduit and signal work ongoing.
- Flying poles October 24th.
- Curb and sidewalk ongoing.
- Asphalt paving moved to October 29th.
- Idaho Power adjusting lines starting October 28th on 2nd Street.
Share October 17, 2024 on Facebook
Share October 17, 2024 on Linkedin
Email October 17, 2024 link
Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st
2nd Street and State Street
- 2nd and State intersection closed
- Silva Cells installed
- Light pole bases, conduit and signal work ongoing
- Curb and sidewalk being prepped
- Curb and sidewalk being placed October 10th – October 22nd
- Asphalt paving anticipated October 24th
Share October 10, 2024 on Facebook
Share October 10, 2024 on Linkedin
Email October 10, 2024 link
Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells being installed.
- Light pole bases, conduit and signal work ongoing.
- Curb and sidewalk being prepped.
- Curb and sidewalk being placed October 10th – October 22nd.
- Asphalt paving anticipated October 24th.