Downtown Eagle Mobility Improvements: Eagle Road and State Street

Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Facebook Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Twitter Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Linkedin Email Downtown Eagle Mobility Improvements: Eagle Road and State Street link

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

  • November 15, 2024

    Share November 15, 2024 on Facebook Share November 15, 2024 on Twitter Share November 15, 2024 on Linkedin Email November 15, 2024 link

    Eagle Road in front of Albertsons

    • Idaho Power poles relocated.
    • Once 2nd street is open, moving back to finish Eagle Rd.

    2nd Street and State Street

    • State Street open heading east and west.
    • Silva Cells installed.
    • Signal installed.
    • Curb and sidewalk ongoing.
    • 2nd Street crosswalk being placed.


  • November 7, 2024

    Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 link

    Eagle Road in front of Albertsons

    • Idaho Power poles relocated.
    • Once 2nd street is open, moving back to finish Eagle Rd.

    2nd Street and State Street

    • State Street open heading east and west.
    • Silva Cells installed.
    • Signal installed.
    • Curb and sidewalk ongoing.
    • 2nd Street crosswalk being placed.
  • November 1, 2024

    Share November 1, 2024 on Facebook Share November 1, 2024 on Twitter Share November 1, 2024 on Linkedin Email November 1, 2024 link

    Eagle Road in front of Albertsons

    • Idaho Power poles relocated.
    • Once 2nd street is open - moving back over to finish Eagle Rd.

    2nd Street and State Street

    • 2nd and State intersection closed.
    • Silva cells installed.
    • Signal installed.
    • Curb and sidewalk ongoing.
    • Asphalt complete.


  • October 24, 2024

    Share October 24, 2024 on Facebook Share October 24, 2024 on Twitter Share October 24, 2024 on Linkedin Email October 24, 2024 link

    Eagle Road in front of Albertsons

    • Idaho Power relocating poles

    2nd Street and State Street

    • 2nd and State intersection closed.
    • Silva Cells installed.
    • Light pole bases, conduit and signal work ongoing.
    • Flying poles October 24th.
    • Curb and sidewalk ongoing.
    • Asphalt paving moved to October 29th.
    • Idaho Power adjusting lines starting October 28th on 2nd Street.


  • October 17, 2024

    Share October 17, 2024 on Facebook Share October 17, 2024 on Twitter Share October 17, 2024 on Linkedin Email October 17, 2024 link

    Eagle Road in front of Albertsons

    • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st

    2nd Street and State Street

    • 2nd and State intersection closed
    • Silva Cells installed
    • Light pole bases, conduit and signal work ongoing
    • Curb and sidewalk being prepped
    • Curb and sidewalk being placed October 10th – October 22nd
    • Asphalt paving anticipated October 24th
  • October 10, 2024

    Share October 10, 2024 on Facebook Share October 10, 2024 on Twitter Share October 10, 2024 on Linkedin Email October 10, 2024 link

    Eagle Road in front of Albertsons

    • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.

    2nd Street and State Street

    • 2nd and State intersection closed.
    • Silva cells being installed.
    • Light pole bases, conduit and signal work ongoing.
    • Curb and sidewalk being prepped.
    • Curb and sidewalk being placed October 10th – October 22nd.
    • Asphalt paving anticipated October 24th.


  • Pedestrian Detour Map

    Share Pedestrian Detour Map on Facebook Share Pedestrian Detour Map on Twitter Share Pedestrian Detour Map on Linkedin Email Pedestrian Detour Map link

  • October 4, 2024

    Share October 4, 2024 on Facebook Share October 4, 2024 on Twitter Share October 4, 2024 on Linkedin Email October 4, 2024 link

    Eagle Road in front of Albertsons

    • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.

    2nd Street and State Street

    • 2nd and State intersection closed starting September 25th.
    • Signal pole bases being placed.
    • Concrete removed on North side.
    • Storm drain complete.
    • Silva Cells being installed.
    • Light pole bases, conduit and signal work ongoing.
    • Curb and sidewalk being prepped.
  • September 26, 2024

    Share September 26, 2024 on Facebook Share September 26, 2024 on Twitter Share September 26, 2024 on Linkedin Email September 26, 2024 link

    Eagle Road in front of Albertsons

    • Pavement markings remaining.
    • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.

    2nd Street and State Street

    • 2nd and State intersection closed starting September 25th.
    • Signal pole bases being placed.
    • Concrete removed on north side.
    • Storm drain and Veola water work ongoing.
    • Historic lights being removed September 30th.
    • Electrical conduit being placed afterwards.


  • State (Old State) & 2nd Intersection Closure - Detour Map

    Share State (Old State) & 2nd Intersection Closure - Detour Map on Facebook Share State (Old State) & 2nd Intersection Closure - Detour Map on Twitter Share State (Old State) & 2nd Intersection Closure - Detour Map on Linkedin Email State (Old State) & 2nd Intersection Closure - Detour Map link


    Beginning Wednesday, the intersection of State Street (Old State) and 2nd Street in Eagle will be fully closed to vehicle traffic.

    Currently, the road is open to eastbound traffic, with 2nd Street being closed just north of the intersection. Closing the intersection of State and 2nd Streets will allow the contractor to keep on schedule, as well as increase safety for vehicles and pedestrians in the area.

    Commuters should use Eagle Road and Plaza Drive to get around the closure. Only local traffic will be allowed on State Street between Eagle Road and Plaza Drive. (see updated detour map)

    The intersection is scheduled to reopen at the end of October.


    The roadwork is part of ACHD's Downtown Eagle Mobility Improvement Project. Phase one of the project is expected to be complete this fall, with phase two starting after phase one is completed. The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

    Underground utility work is also being done in tandem with ACHD’s project in an effort to minimize the impact to businesses and residents.

    During the roadwork, access will be maintained to all businesses in downtown Eagle, and businesses are ready and eager to serve their customers.




Page last updated: 15 Nov 2024, 10:45 AM