Downtown Eagle Mobility Improvements: Eagle Road and State Street

Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Facebook Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Twitter Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Linkedin Email Downtown Eagle Mobility Improvements: Eagle Road and State Street link

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

  • March 28, 2025

    Share March 28, 2025 on Facebook Share March 28, 2025 on Twitter Share March 28, 2025 on Linkedin Email March 28, 2025 link
    28 Mar 2025

    Eagle Road in front of Albertsons

    • Culvert complete.
    • Retaining wall ongoing.
    • Paving complete.
    • Pavement markings complete.
    • Swale ongoing.
    • Minor items remaining.

    Veolia

    • Working at the intersection of Olde Park and State Street
      • Night work 8pm – 7am - TBD
    • Starting on Aikens between 2nd and Eagle.

    Olde Park Place

    • Storm Drain and irrigation complete.
    • Excavation and backfill ongoing. Electrical and landscaping ongoing.
    • Working in State Street working on Silva Cells.
    • Placing structural fill.
    • Curb and gutter starting first week of April.

    Aikens between 2nd and Eagle

    • Eagle Sewer is complete.
    • Sub grading road.


  • March 20, 2024

    Share March 20, 2024 on Facebook Share March 20, 2024 on Twitter Share March 20, 2024 on Linkedin Email March 20, 2024 link
    20 Mar 2025

    Eagle Road in front of Albertsons

    • Culvert complete.
    • Retaining wall ongoing.
    • Curb and gutter getting placed.
    • Swale ongoing.
    • Paving anticipated March 21st.
    • Concrete median anticipated start March 24th.

    Veolia

    • Working at the intersection of Olde Park and State Street - Night work 8pm – 7am - Pending Veolia’s contractor schedule.

    Olde Park

    • Storm drain and irrigation complete.
    • Excavation and backfill ongoing.
    • Electrical and landscaping ongoing.
    • Working in State Street working on Silva Cells.

    Aikens between 2nd and Eagle

    • Waiting for Eagle Sewer’s contractor to be complete.


  • March 14, 2025

    Share March 14, 2025 on Facebook Share March 14, 2025 on Twitter Share March 14, 2025 on Linkedin Email March 14, 2025 link
    14 Mar 2025

    Eagle Road in front of Albertsons

    • Culvert complete
    • Retaining wall ongoing
    • Curb and gutter getting placed
    • Swale ongoing
    • Approach at Albertsons ongoing


    Veolia

    • Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.


    Olde Park Place

    • Storm Drain and Irrigation complete
    • Excavation and backfill ongoing
    • Electrical and landscaping ongoing
    • Working in State Street working on Silva Cells


  • March 6, 2025

    Share March 6, 2025 on Facebook Share March 6, 2025 on Twitter Share March 6, 2025 on Linkedin Email March 6, 2025 link
    14 Mar 2025

    Eagle Road in front of Albertsons

    • Culvert complete.
    • Retaining wall installed after the backfill complete.
    • Curb and gutter anticipated starting March 10th.
    • Swale ongoing.
    • Approach at Albertsons ongoing.

    Veolia

    • Working at the intersection of Olde Park and State Street.
    • Night work 8pm – 7am.

    Olde Park

    • Storm drain and irrigation ongoing.
    • Sub grading after underground is work complete.
    • Electrical and landscaping underground will be after the irrigation line is installed.
    • Working on State Street to install silva cells.
  • February 28, 2025

    Share February 28, 2025 on Facebook Share February 28, 2025 on Twitter Share February 28, 2025 on Linkedin Email February 28, 2025 link
    28 Feb 2025

    Eagle Road in front of Albertsons

    • Culvert complete.
    • Backfilling starting March 3rd.
    • Retaining wall after backfill complete.
    • Curb and gutter anticipated starting March 10th.
    • Swale ongoing.

    Veolia

    • Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.

    Olde Park

    • Storm Drain and Irrigation ongoing.
    • Sub grading after underground work complete.
    • Electrical and landscaping underground will be after irrigation line installed.
  • February 20, 2025

    Share February 20, 2025 on Facebook Share February 20, 2025 on Twitter Share February 20, 2025 on Linkedin Email February 20, 2025 link
    20 Feb 2025

    Eagle Road in front of Albertsons

    • Culvert ongoing.
    • Floor placed, working on walls.
    • Walls complete, lid ongoing.
    • Swale ongoing.


    Phase 2

    • Clearing and grubbing Aikens Street for utilities to relocate lines.
    • Veolia working on Aikens installing new waterline.
    • Eagle Sewer starting February 3rd on 2nd Street.
    • Storm drain and irrigation will begin once Veolia is complete.
  • February 14, 2025

    Share February 14, 2025 on Facebook Share February 14, 2025 on Twitter Share February 14, 2025 on Linkedin Email February 14, 2025 link
    14 Feb 2025

    Eagle Road in front of Albertsons

    • Culvert ongoing.
    • Floor placed, working on walls.
    • Swale ongoing.

    Phase 2

    • Clearing and grubbing Aikens Street for utilities to relocate lines.
    • Veolia working on Aikens installing new waterline.
    • Eagle Sewer starting February 3rd on 2nd Street.
    • Storm drain and irrigation will begin once Veolia is complete.
  • February 7, 2025

    Share February 7, 2025 on Facebook Share February 7, 2025 on Twitter Share February 7, 2025 on Linkedin Email February 7, 2025 link
    07 Feb 2025

    Eagle Road In Front Of Albertsons

    • Culvert ongoing
    • Swale ongoing

    Eagle Road and State Street - Phase 2

    • Clearing and grubbing Aikens Street for utilities to relocate lines.
    • Veolia working on Aikens installing new waterline.
    • Eagle Sewer starting February 3rd on 2nd Street.
    • Storm drain and irrigation once Veolia is complete.
  • January 31, 2025

    Share January 31, 2025 on Facebook Share January 31, 2025 on Twitter Share January 31, 2025 on Linkedin Email January 31, 2025 link
    31 Jan 2025

    Eagle Road in front of Albertsons

    • Culvert ongoing.
    • Swale ongoing.

    Phase 2

    • Clearing and grubbing Aikens Street for utilities to relocate lines.
    • Veolia working on Aikens installing new waterline.
    • Eagle Sewer starting Feb 3rd on 2nd Street.
  • Phase 2- Aikens and Olde Park Place Closures

    Share Phase 2- Aikens and Olde Park Place Closures on Facebook Share Phase 2- Aikens and Olde Park Place Closures on Twitter Share Phase 2- Aikens and Olde Park Place Closures on Linkedin Email Phase 2- Aikens and Olde Park Place Closures link
    24 Jan 2025
    Phase 2 of the Downtown Eagle Mobility Improvements project is expected to begin next week.
    Beginning Monday, Aikens Street in Eagle will be closed from Olde Park Place to east of 1st Street, where the street currently ends. Additionally, Olde Park Place will be closed between State Street (Old State) and Aikens Street.
    Business and residential access will be maintained during the closure. To help accommodate local access, 1st Street will temporary become a two-way street from Aikens Street up to the alley. The alley will temporarily be a one-way alley for eastbound traffic only. (See detour map)
    These closures and temporary access points are expected to be in place until spring of 2025.
Page last updated: 28 Mar 2025, 12:08 PM