Downtown Eagle Mobility Improvements: Eagle Road and State Street
The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.
The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.
Goals
The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.
The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.
The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.
Goals
The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.
-
March 28, 2025
Share March 28, 2025 on Facebook Share March 28, 2025 on Twitter Share March 28, 2025 on Linkedin Email March 28, 2025 link28 Mar 2025Eagle Road in front of Albertsons
- Culvert complete.
- Retaining wall ongoing.
- Paving complete.
- Pavement markings complete.
- Swale ongoing.
- Minor items remaining.
Veolia
- Working at the intersection of Olde Park and State Street
- Night work 8pm – 7am - TBD
- Starting on Aikens between 2nd and Eagle.
Olde Park Place
- Storm Drain and irrigation complete.
- Excavation and backfill ongoing. Electrical and landscaping ongoing.
- Working in State Street working on Silva Cells.
- Placing structural fill.
- Curb and gutter starting first week of April.
Aikens between 2nd and Eagle
- Eagle Sewer is complete.
- Sub grading road.
-
March 20, 2024
Share March 20, 2024 on Facebook Share March 20, 2024 on Twitter Share March 20, 2024 on Linkedin Email March 20, 2024 link20 Mar 2025Eagle Road in front of Albertsons
- Culvert complete.
- Retaining wall ongoing.
- Curb and gutter getting placed.
- Swale ongoing.
- Paving anticipated March 21st.
- Concrete median anticipated start March 24th.
Veolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am - Pending Veolia’s contractor schedule.
Olde Park
- Storm drain and irrigation complete.
- Excavation and backfill ongoing.
- Electrical and landscaping ongoing.
- Working in State Street working on Silva Cells.
Aikens between 2nd and Eagle
- Waiting for Eagle Sewer’s contractor to be complete.
-
March 14, 2025
Share March 14, 2025 on Facebook Share March 14, 2025 on Twitter Share March 14, 2025 on Linkedin Email March 14, 2025 link14 Mar 2025Eagle Road in front of Albertsons
- Culvert complete
- Retaining wall ongoing
- Curb and gutter getting placed
- Swale ongoing
- Approach at Albertsons ongoing
Veolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.
Olde Park Place
- Storm Drain and Irrigation complete
- Excavation and backfill ongoing
- Electrical and landscaping ongoing
- Working in State Street working on Silva Cells
-
March 6, 2025
Share March 6, 2025 on Facebook Share March 6, 2025 on Twitter Share March 6, 2025 on Linkedin Email March 6, 2025 link14 Mar 2025Eagle Road in front of Albertsons
- Culvert complete.
- Retaining wall installed after the backfill complete.
- Curb and gutter anticipated starting March 10th.
- Swale ongoing.
- Approach at Albertsons ongoing.
Veolia
- Working at the intersection of Olde Park and State Street.
- Night work 8pm – 7am.
Olde Park
- Storm drain and irrigation ongoing.
- Sub grading after underground is work complete.
- Electrical and landscaping underground will be after the irrigation line is installed.
- Working on State Street to install silva cells.
-
February 28, 2025
Share February 28, 2025 on Facebook Share February 28, 2025 on Twitter Share February 28, 2025 on Linkedin Email February 28, 2025 link28 Feb 2025Eagle Road in front of Albertsons
- Culvert complete.
- Backfilling starting March 3rd.
- Retaining wall after backfill complete.
- Curb and gutter anticipated starting March 10th.
- Swale ongoing.
Veolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.
Olde Park
- Storm Drain and Irrigation ongoing.
- Sub grading after underground work complete.
- Electrical and landscaping underground will be after irrigation line installed.
-
February 20, 2025
Share February 20, 2025 on Facebook Share February 20, 2025 on Twitter Share February 20, 2025 on Linkedin Email February 20, 2025 link20 Feb 2025Eagle Road in front of Albertsons
- Culvert ongoing.
- Floor placed, working on walls.
- Walls complete, lid ongoing.
- Swale ongoing.
Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting February 3rd on 2nd Street.
- Storm drain and irrigation will begin once Veolia is complete.
-
February 14, 2025
Share February 14, 2025 on Facebook Share February 14, 2025 on Twitter Share February 14, 2025 on Linkedin Email February 14, 2025 link14 Feb 2025Eagle Road in front of Albertsons
- Culvert ongoing.
- Floor placed, working on walls.
- Swale ongoing.
Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting February 3rd on 2nd Street.
- Storm drain and irrigation will begin once Veolia is complete.
-
February 7, 2025
Share February 7, 2025 on Facebook Share February 7, 2025 on Twitter Share February 7, 2025 on Linkedin Email February 7, 2025 link07 Feb 2025Eagle Road In Front Of Albertsons
- Culvert ongoing
- Swale ongoing
Eagle Road and State Street - Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting February 3rd on 2nd Street.
- Storm drain and irrigation once Veolia is complete.
-
January 31, 2025
Share January 31, 2025 on Facebook Share January 31, 2025 on Twitter Share January 31, 2025 on Linkedin Email January 31, 2025 link31 Jan 2025Eagle Road in front of Albertsons
- Culvert ongoing.
- Swale ongoing.
Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting Feb 3rd on 2nd Street.
-
Phase 2- Aikens and Olde Park Place Closures
Share Phase 2- Aikens and Olde Park Place Closures on Facebook Share Phase 2- Aikens and Olde Park Place Closures on Twitter Share Phase 2- Aikens and Olde Park Place Closures on Linkedin Email Phase 2- Aikens and Olde Park Place Closures link24 Jan 2025Phase 2 of the Downtown Eagle Mobility Improvements project is expected to begin next week.Beginning Monday, Aikens Street in Eagle will be closed from Olde Park Place to east of 1st Street, where the street currently ends. Additionally, Olde Park Place will be closed between State Street (Old State) and Aikens Street.These closures and temporary access points are expected to be in place until spring of 2025.
Related projects
Live Projects
Materials from Phase 2 Construction Open House
Construction Open House
-
January 23 2025
-
January 31 2024
Monthly Public Pop Up
-
August 29 2024
-
July 20 2024
-
June 27 2024
-
May 30 2024
-
April 25 2024
Drone Footage
-
March 11 2025
-
November 13 2024
-
October 10 2024
-
September 13 2024
-
August 23 2024
Materials from Construction Open House
Follow Project
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email projects@achdidaho.org (External link) -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org (External link) -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org (External link)
History
The design was the outcome of the Eagle Road and States Street Concept Design, an effort that began in 2012. After working with the community and the City of Eagle to evaluate multiple alternatives, the ACHD Commission approved the City's request to design and construct the Quadrant Alternative. This alternative best balances the need to safely accommodate the expected traffic growth, minimize impacts to adjacent properties and parking, and make downtown Eagle more walkable and bikeable, as well as being respectful of downtown's history and small town feel.