Downtown Eagle Mobility Improvements: Eagle Road and State Street

Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Facebook Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Twitter Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Linkedin Email Downtown Eagle Mobility Improvements: Eagle Road and State Street link

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link

    Eagle Road between Plaza and Aikens

    • Veolia will need to close Eagle Road at Aikens for water change over. Anticipated August 5th for a week - night work only.

    Front of Albertsons

    • Working on Plaza side.
    • Retaining wall construction ongoing.
    • North side of Plaza started July 19th - One approach at a time.

    Eagle and Plaza Intersection

    • Paving on Eagle complete.
    • Signal at Eagle and Plaza was turned on July 18th.
  • July 19, 2024

    Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link

    Eagle Road between Plaza and Aikens

    • Veolia will need to close Eagle Road at Aikens for a water change over - Anticipated once construction has been completed on Plaza.

    Front of Albertsons

    • Working on Plaza side. Construction of retaining wall ongoing.
    • North side of Plaza started July 19th - One approach at a time will be constructed.

    Eagle and Plaza Intersection

    • Paving on Eagle complete.
    • Signal at Eagle and Plaza was turned on July 18th.


  • July 17, 2024 - Eagle Saturday Market

    Share July 17, 2024 - Eagle Saturday Market on Facebook Share July 17, 2024 - Eagle Saturday Market on Twitter Share July 17, 2024 - Eagle Saturday Market on Linkedin Email July 17, 2024 - Eagle Saturday Market link

    Please join ACHD staff on Saturday, July 20th from 9:00 a.m. to 12:00 p.m. at the Eagle Saturday Market.

    ACHD staff will be on site to share with you the progress of the project and answer any questions from the businesses and public. See you Saturday!

  • July 12, 2023

    Share July 12, 2023 on Facebook Share July 12, 2023 on Twitter Share July 12, 2023 on Linkedin Email July 12, 2023 link
    • Eagle Road between Plaza and Aikens
      • Veolia will need to shut down Aikens for water change over - after Eagle Fun Days
    • Front of Albertsons - East side of Eagle between Highway 44 and Plaza.
      • Utilities relocating. Concrete ongoing. Will be working on Plaza side. Retaining wall ongoing.
    • Eagle and Plaza Intersection
      • Removing Asphalt. Grading road. Paving anticipated for the week of July 15th.
  • July 10, 2024

    Share July 10, 2024 on Facebook Share July 10, 2024 on Twitter Share July 10, 2024 on Linkedin Email July 10, 2024 link

    ACHD will be milling and paving Eagle Road between Plaza and HWY 44 beginning Thursday, July 11th. While Eagle Road will not be closed, there will be lane shifts and long delays throughout this process. We advise that you take an alternative route, such as Old State, to get around the delays.

    Plaza Drive will be closed for Eagle Fun Days beginning Friday evening. Part of Plaza, from Eagle to the McDonald's approach, will also be milled and paved while the road is closed. We expect work to be complete late next week.

    But have no fear! Work will be paused so the fun can go on! Saturday will be all about Eagle Fun Days and construction will restart on Sunday.

    In other exciting news, late next week, Plaza Drive will be reopened and the light at the intersection of Plaza and Eagle will be turned back on. In addition, State HWY 55 and HWY 44 lane restrictions will be removed on July 19th.

    Please note that there is still business access throughout construction. Don't forget to support your local businesses!

  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link

    Eagle Road between Plaza and Aikens

    • 4-Way Stop at Eagle & Plaza.
    • Bottom lift paving between Plaza & Aikens complete.
    • Veolia will need to shut down Aikens for water change over - waiting until after Eagle Fun Days.

    Eagle Road and Plaza Intersection

    • Contractor will be paving in the next three weeks at Eagle & Plaza.
    • Curb & Gutter anticipated to be placed on Eagle and Plaza.
    • Removal of Asphalt July 10th- 12th (Tentative)

    Front of Albertsons - East side of Eagle between Highway 44 and Plaza

    • Utilities relocating.
    • Concrete ongoing.
    • Continued work on Plaza side.
    • Boring under canal.

    What to expect in the next few weeks

    • Expect heavy congestion
    • Temporary road closure at Plaza Dr.
    • Shifting road patterns
    • Signal turn on expected July 18th
    • Traffic control devices will be removed from Highway 44 & 55 anticipated by July 18th.

  • June 21, 2024

    Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link

    Eagle Road between Plaza and Aikens

    • 4-Way Stop at Eagle & Plaza.
    • Bottom lift paving between Plaza & Aikens complete.
    • Veolia will need to shut down Aikens for water change over - Waiting until after Eagle Fun days

    Front of Albertsons - East side of Eagle between Highway 44 and Plaza

    • Utilities relocating.
    • Concrete ongoing.
    • Will be working on Plaza side - Boring under canal.
  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link
    • Stage 1 -Eagle Road between Plaza and Aikens
      • 4-Way Stop at Eagle & Plaza
      • Bottom lift paving between Plaza & Aikens complete
      • Veolia will need to shut down Aikens for water change over
    • Stage 2 – Front of Albertsons
      • East side of Eagle between Highway 44 and Plaza
      • Utilities relocating
      • Concrete ongoing
      • Will be working on Plaza side
      • Boring under canal
  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link
    • Stage 1 -Eagle Road between Plaza and Aikens
      • 4-Way Stop at Eagle & Plaza
      • Bottom lift paving between Plaza & Aikens complete
      • Veolia will need to shut down Aikens for water change over
    • Stage 2 – Front of Albertsons
      • East side of Eagle between Highway 44 and Plaza
      • Utilities relocating
      • Concrete ongoing
      • Will be working on Plaza side


  • May 31, 2024

    Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link
    • Stage 1 - Eagle Road between Plaza and Aikens
      • 4-Way Stop at Eagle & Plaza.
      • Bottom lift paving between Plaza & Aikens complete.
      • Veolia will need to shut down Aikens for water change over.
    • Stage 2 – Front of Albertsons - East side of Eagle between Highway 44 and Plaza
      • Utilities relocating.
      • Concrete ongoing.
      • Crews will be working on Plaza side.
Page last updated: 26 Jul 2024, 10:56 AM