Downtown Eagle Mobility Improvements: Eagle Road and State Street

Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Facebook Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Twitter Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Linkedin Email Downtown Eagle Mobility Improvements: Eagle Road and State Street link

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

  • May 8, 2025

    08 May 2025
    Share May 8, 2025 on Facebook Share May 8, 2025 on Twitter Share May 8, 2025 on Linkedin Email May 8, 2025 link

    Olde Park Place

    • Landscape ongoing.
    • Brick pavers installation.

    Aikens between 2nd and Eagle

    • Placing silva cells.
    • Placing ¾” aggregate for road base.
    • Electrical work ongoing.
    • Curb anticipated week of May 5th.

    Olde Park to Eagle Rd

    • Road closure anticipated May 5th – end of May.
    • Veolia installing water.
    • Silva cells ongoing.
    • Prepping and placing sidewalk crossings.
  • May 1, 2025

    01 May 2025
    Share May 1, 2025 on Facebook Share May 1, 2025 on Twitter Share May 1, 2025 on Linkedin Email May 1, 2025 link

    Olde Park

    • Landscape ongoing

    Aikens between 2nd and Eagle

    • Placing Silva Cells
    • Placing ¾” aggregate for road base
    • Electrical work ongoing
    • Curb anticipated week of May 5th

    Olde Park To Eagle Rd

    • Road closure anticipated May 5th – May 30th
    • Veolia installing water
    • Silva cells ongoing
    • Prepping and placing sidewalk crossings
  • May 1, 2025 - New Detour Map & Information

    01 May 2025
    Share May 1, 2025 - New Detour Map & Information on Facebook Share May 1, 2025 - New Detour Map & Information on Twitter Share May 1, 2025 - New Detour Map & Information on Linkedin Email May 1, 2025 - New Detour Map & Information link

    State (Old State) between Olde Park Place and Eagle Road will be closed from

    May 5th through the end of May.

  • April 25, 2025

    25 Apr 2025
    Share April 25, 2025 on Facebook Share April 25, 2025 on Twitter Share April 25, 2025 on Linkedin Email April 25, 2025 link

    Veolia

    • Working at the intersection of Olde Park and State Street
    • Lane shifts to install crossings
    • Started Aikens and 2nd on March 31st - Complete.

    Olde Park

    • Paving complete.
    • Concrete collars and pavement markings ongoing.
    • Landscape ongoing.

    Aikens between 2nd and Eagle

    • Placing Silva Cells.
    • Placing ¾” aggregate for road base.
    • Storm drain and irrigation complete.
    • Electrical work ongoing.

    Olde Park To Eagle Rd on State (Old State)

    • Road closure anticipated second week of May through end of May.


  • April 17, 2025

    17 Apr 2025
    Share April 17, 2025 on Facebook Share April 17, 2025 on Twitter Share April 17, 2025 on Linkedin Email April 17, 2025 link

    Veolia

    • Working at the intersection of Olde Park and State Street.
    • Lane shifts to install crossings.
    • Starting Aikens and 2nd on March 31st - Complete.

    Olde Park

    • Silva Cells ongoing.
    • Electrical and landscaping ongoing.
    • Working in State Street on Silva Cells.
    • Curb and gutter ongoing.
    • Paving anticipated the week of April 21st.
    • Pavement markings after paving.

    Aikens between 2nd and Eagle

    • Sub grading road.
    • Placing Silva Cells.
    • Storm drain and irrigation ongoing.
    • Electrical work ongoing.


  • April 11, 2025

    11 Apr 2025
    Share April 11, 2025 on Facebook Share April 11, 2025 on Twitter Share April 11, 2025 on Linkedin Email April 11, 2025 link

    Veolia

    • Working at the intersection of Olde Park and State Street.
    • Lane shifts to install crossings.
    • Starting Aikens and 2nd on March 31st - Complete.

    Olde Park

    • Silva Cells ongoing.
    • Electrical and landscaping ongoing.
    • Working in State Street on Silva Cells.
    • Curb and gutter ongoing.
    • Paving anticipated the week of April 14th.
    • Pavement markings.

    Aikens between 2nd and Eagle

    • Sub grading road.
    • Placing Silva Cells.
    • Storm drain and irrigation ongoing.
    • Electrical work ongoing.


  • April 4, 2025

    04 Apr 2025
    Share April 4, 2025 on Facebook Share April 4, 2025 on Twitter Share April 4, 2025 on Linkedin Email April 4, 2025 link

    Veolia

    • Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.TBD.
    • Starting Aikens and 2nd on March 31 - ongoing.

    Olde Park

    • Silva cells ongoing.
    • Electrical and landscaping ongoing.
    • Working in State Street working on Silva Cells.
    • Placing structural fill.
    • Curb and gutter ongoing.

    Aikens between 2nd and Eagle

    • Sub grading road.
    • Placing silva cells.
    • Storm drain and irrigation.


  • March 28, 2025

    28 Mar 2025
    Share March 28, 2025 on Facebook Share March 28, 2025 on Twitter Share March 28, 2025 on Linkedin Email March 28, 2025 link

    Eagle Road in front of Albertsons

    • Culvert complete.
    • Retaining wall ongoing.
    • Paving complete.
    • Pavement markings complete.
    • Swale ongoing.
    • Minor items remaining.

    Veolia

    • Working at the intersection of Olde Park and State Street
      • Night work 8pm – 7am - TBD
    • Starting on Aikens between 2nd and Eagle.

    Olde Park Place

    • Storm Drain and irrigation complete.
    • Excavation and backfill ongoing. Electrical and landscaping ongoing.
    • Working in State Street working on Silva Cells.
    • Placing structural fill.
    • Curb and gutter starting first week of April.

    Aikens between 2nd and Eagle

    • Eagle Sewer is complete.
    • Sub grading road.


  • March 20, 2024

    20 Mar 2025
    Share March 20, 2024 on Facebook Share March 20, 2024 on Twitter Share March 20, 2024 on Linkedin Email March 20, 2024 link

    Eagle Road in front of Albertsons

    • Culvert complete.
    • Retaining wall ongoing.
    • Curb and gutter getting placed.
    • Swale ongoing.
    • Paving anticipated March 21st.
    • Concrete median anticipated start March 24th.

    Veolia

    • Working at the intersection of Olde Park and State Street - Night work 8pm – 7am - Pending Veolia’s contractor schedule.

    Olde Park

    • Storm drain and irrigation complete.
    • Excavation and backfill ongoing.
    • Electrical and landscaping ongoing.
    • Working in State Street working on Silva Cells.

    Aikens between 2nd and Eagle

    • Waiting for Eagle Sewer’s contractor to be complete.


  • March 14, 2025

    14 Mar 2025
    Share March 14, 2025 on Facebook Share March 14, 2025 on Twitter Share March 14, 2025 on Linkedin Email March 14, 2025 link

    Eagle Road in front of Albertsons

    • Culvert complete
    • Retaining wall ongoing
    • Curb and gutter getting placed
    • Swale ongoing
    • Approach at Albertsons ongoing


    Veolia

    • Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.


    Olde Park Place

    • Storm Drain and Irrigation complete
    • Excavation and backfill ongoing
    • Electrical and landscaping ongoing
    • Working in State Street working on Silva Cells