Veolia

  • Working at the intersection of Olde Park and State Street.
  • Lane shifts to install crossings.
  • Starting Aikens and 2nd on March 31st - Complete.

Olde Park

  • Silva Cells ongoing.
  • Electrical and landscaping ongoing.
  • Working in State Street on Silva Cells.
  • Curb and gutter ongoing.
  • Paving anticipated the week of April 21st.
  • Pavement markings after paving.

Aikens between 2nd and Eagle

  • Sub grading road.
  • Placing Silva Cells.
  • Storm drain and irrigation ongoing.
  • Electrical work ongoing.


Share April 17, 2025 on Facebook Share April 17, 2025 on X (formerly Twitter) Share April 17, 2025 on Linkedin Email April 17, 2025 link

This project is substantially complete. 