April 17, 2025

Veolia

  • Working at the intersection of Olde Park and State Street.
  • Lane shifts to install crossings.
  • Starting Aikens and 2nd on March 31st - Complete.

Olde Park

  • Silva Cells ongoing.
  • Electrical and landscaping ongoing.
  • Working in State Street on Silva Cells.
  • Curb and gutter ongoing.
  • Paving anticipated the week of April 21st.
  • Pavement markings after paving.

Aikens between 2nd and Eagle

  • Sub grading road.
  • Placing Silva Cells.
  • Storm drain and irrigation ongoing.
  • Electrical work ongoing.


Share April 17, 2025 on Facebook Share April 17, 2025 on Twitter Share April 17, 2025 on Linkedin Email April 17, 2025 link

This project is substantially complete. 