April 19, 2024
- Eagle Road Closure April 15th – April 30th between Plaza and Aikens
- 3-Way Stop implemented at Eagle and Plaza.
- Bore under canal starting April 10th - ongoing.
- Veolia water line to Aikens.
- Building grade for curb.
- Curb anticipated to be placed April 25th.
- Signal Poles being placed April 18th.
- Flagging during placement.
- Landscaping wall ongoing.
Share April 19, 2024 on Facebook
Share April 19, 2024 on X (formerly Twitter)
Share April 19, 2024 on Linkedin
Email April 19, 2024 link
This project is substantially complete.