  • Eagle Road Closure April 15th – April 30th between Plaza and Aikens
  • 3-Way Stop implemented at Eagle and Plaza.
  • Bore under canal starting April 10th - ongoing.
  • Veolia water line to Aikens.
  • Building grade for curb.
  • Curb anticipated to be placed April 25th.
  • Signal poles placed.
  • Landscaping wall ongoing.