Veolia
- Working at the intersection of Olde Park and State Street
- Lane shifts to install crossings
- Started Aikens and 2nd on March 31st - Complete.
Olde Park
- Paving complete.
- Concrete collars and pavement markings ongoing.
- Landscape ongoing.
Aikens between 2nd and Eagle
- Placing Silva Cells.
- Placing ¾” aggregate for road base.
- Storm drain and irrigation complete.
- Electrical work ongoing.
Olde Park To Eagle Rd on State (Old State)
- Road closure anticipated second week of May through end of May.