April 4, 2025
Veolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.TBD.
- Starting Aikens and 2nd on March 31 - ongoing.
Olde Park
- Silva cells ongoing.
- Electrical and landscaping ongoing.
- Working in State Street working on Silva Cells.
- Placing structural fill.
- Curb and gutter ongoing.
Aikens between 2nd and Eagle
- Sub grading road.
- Placing silva cells.
- Storm drain and irrigation.
Share April 4, 2025 on Facebook
Share April 4, 2025 on X (formerly Twitter)
Share April 4, 2025 on Linkedin
Email April 4, 2025 link
This project is substantially complete.