  • Phase 1 - Northeast corner of Eagle and Plaza.
    • Utilities relocating.
    • Signal work ongoing.
    • Landscaping wall ongoing.
  • Plaza and Eagle Closure
    • Closed from April 1st -15th.
    • Veolia tie in water in middle of intersection then proceeding down Plaza.
    • Signal work crossing Eagle Rd.
    • Irrigation and conduits crossing Eagle during closure.
  • Eagle Rd. closure - April 15th - April 30th.
    • Bore under canal starting 4/10.
    • Veolia water line to Aikens.