April 5, 2024
- Phase 1 - Northeast corner of Eagle and Plaza.
- Utilities relocating.
- Signal work ongoing.
- Landscaping wall ongoing.
- Plaza and Eagle Closure
- Closed from April 1st -15th.
- Veolia tie in water in middle of intersection then proceeding down Plaza.
- Signal work crossing Eagle Rd.
- Irrigation and conduits crossing Eagle during closure.
- Eagle Rd. closure - April 15th - April 30th.
- Bore under canal starting 4/10.
- Veolia water line to Aikens.