Olde Park
Landscape and brick pavers ongoing.
Aikens between 2nd and Eagle
Parking lot ongoing. Landscaping ongoing.
Eagle Rd & State Intersection
Started July 7th. Removal of road and signal equipment. Underground electrical work ongoing. Water and storm drain ongoing.
Share August 1, 2025 on Facebook
Share August 1, 2025 on Twitter
Share August 1, 2025 on Linkedin
Email August 1, 2025 link
This project is substantially complete.