August 15, 2025

Olde Park

  • Landscape and brick pavers ongoing.

Aikens between 2nd and Eagle

  • Parking lot ongoing.
  • Landscaping ongoing.
  • Water tie in required for basin.

Eagle Rd & State Intersection

  • Started July 7th
  • Removal of road and signal equipment
  • Underground electrical work ongoing.
  • Water and storm drain ongoing.
  • Curb and gutter being prepped.
  • Concrete ongoing.


Share August 15, 2025 on Facebook Share August 15, 2025 on Twitter Share August 15, 2025 on Linkedin Email August 15, 2025 link

This project is substantially complete. 