August 2, 2024

Eagle Road between Plaza and Aikens

  • Veolia will need to close Aikens for water change over - Anticipated end of August.

Front of Albertsons

  • Will be working on Plaza side.
  • Retaining wall ongoing - North side of Plaza started July 19th - One approach at a time.
  • Albertsons approach anticipating starting August 5th.

Eagle and Plaza Intersection

  • Paving on Eagle complete.
  • Signal at Eagle and Plaza was turned on July 18th.