August 2, 2024
Eagle Road between Plaza and Aikens
- Veolia will need to close Aikens for water change over - Anticipated end of August.
Front of Albertsons
- Will be working on Plaza side.
- Retaining wall ongoing - North side of Plaza started July 19th - One approach at a time.
- Albertsons approach anticipating starting August 5th.
Eagle and Plaza Intersection
- Paving on Eagle complete.
- Signal at Eagle and Plaza was turned on July 18th.