August 29, 2025

Olde Park

  • Landscape and brick pavers ongoing.

Aikens between 2nd and Eagle

  • Parking lot ongoing. Landscaping ongoing. Water tie in required for basin.

Eagle Rd & State Intersection

  • Intersection paved.
  • Concrete collars placed.
  • Sidewalk crossing place - Curing.
  • Signal poles being placed.
  • Anticipated turn for signal September 9th.
  • Curb ongoing on State Street.


Share August 29, 2025 on Facebook Share August 29, 2025 on X (formerly Twitter) Share August 29, 2025 on Linkedin Email August 29, 2025 link

This project is substantially complete. 