August 29, 2025
Olde Park
- Landscape and brick pavers ongoing.
Aikens between 2nd and Eagle
- Parking lot ongoing. Landscaping ongoing. Water tie in required for basin.
Eagle Rd & State Intersection
- Intersection paved.
- Concrete collars placed.
- Sidewalk crossing place - Curing.
- Signal poles being placed.
- Anticipated turn for signal September 9th.
- Curb ongoing on State Street.