February 14, 2025
Eagle Road in front of Albertsons
- Culvert ongoing.
- Floor placed, working on walls.
- Swale ongoing.
Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting February 3rd on 2nd Street.
- Storm drain and irrigation will begin once Veolia is complete.
Share February 14, 2025 on Facebook
Share February 14, 2025 on Twitter
Share February 14, 2025 on Linkedin
Email February 14, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends