February 14, 2025

Eagle Road in front of Albertsons

  • Culvert ongoing.
  • Floor placed, working on walls.
  • Swale ongoing.

Phase 2

  • Clearing and grubbing Aikens Street for utilities to relocate lines.
  • Veolia working on Aikens installing new waterline.
  • Eagle Sewer starting February 3rd on 2nd Street.
  • Storm drain and irrigation will begin once Veolia is complete.