Eagle Road in front of Albertsons
- Culvert ongoing.
- Floor placed, working on walls.
- Walls complete, lid ongoing.
- Swale ongoing.
Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting February 3rd on 2nd Street.
- Storm drain and irrigation will begin once Veolia is complete.
Share February 20, 2025 on Facebook
Share February 20, 2025 on X (formerly Twitter)
Share February 20, 2025 on Linkedin
Email February 20, 2025 link
This project is substantially complete.