Eagle Road in front of Albertsons
- Culvert complete.
- Backfilling starting March 3rd.
- Retaining wall after backfill complete.
- Curb and gutter anticipated starting March 10th.
- Swale ongoing.
Veolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.
Olde Park
- Storm Drain and Irrigation ongoing.
- Sub grading after underground work complete.
- Electrical and landscaping underground will be after irrigation line installed.
Share February 28, 2025 on Facebook
Share February 28, 2025 on X (formerly Twitter)
Share February 28, 2025 on Linkedin
Email February 28, 2025 link
This project is substantially complete.