February 7, 2025
Eagle Road In Front Of Albertsons
- Culvert ongoing
- Swale ongoing
Eagle Road and State Street - Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting February 3rd on 2nd Street.
- Storm drain and irrigation once Veolia is complete.
Share February 7, 2025 on Facebook
Share February 7, 2025 on X (formerly Twitter)
Share February 7, 2025 on Linkedin
Email February 7, 2025 link
This project is substantially complete.