January 31, 2025
Eagle Road in front of Albertsons
- Culvert ongoing.
- Swale ongoing.
Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting Feb 3rd on 2nd Street.
Share January 31, 2025 on Facebook
Share January 31, 2025 on X (formerly Twitter)
Share January 31, 2025 on Linkedin
Email January 31, 2025 link
This project is substantially complete.