January 31, 2025
Eagle Road in front of Albertsons
- Culvert ongoing.
- Swale ongoing.
Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting Feb 3rd on 2nd Street.