January 31, 2025

Eagle Road in front of Albertsons

  • Culvert ongoing.
  • Swale ongoing.

Phase 2

  • Clearing and grubbing Aikens Street for utilities to relocate lines.
  • Veolia working on Aikens installing new waterline.
  • Eagle Sewer starting Feb 3rd on 2nd Street.