Construction of the Downtown Eagle Mobility Improvements: Eagle Road and State Street project has been split into two phases:
Phase 1 – Scheduled To Start Construction Early 2024 And To Be Completed In The Fall Of 2024:
- Eagle Road, SH-44 to the canal (just north of Plaza Drive) – Reconstructing the road with concrete and asphalt paving and replacing the sidewalk
- This includes expanding the Eagle Road and Plaza Drive intersection with concrete pavement
- 2 through lanes in each direction on Eagle Road
- 2 left turns lanes to get from Plaza Drive to Eagle Road
- Eagle Road will not be widened above the canal
- This includes expanding the Eagle Road and Plaza Drive intersection with concrete pavement
- Plaza Drive, Eagle Road to 2nd Street – Repave with asphalt pavement, replacing some sidewalk
- State Street and 2nd Street intersection – Add a traffic signal and repave with asphalt pavement
- Replacing some on-street parking on State Street with left turn lanes
- Phase 1 map
Phase 2 – Scheduled To Start Construction In Fall 2024 And To Be Completed In The Fall Of 2025:
- Eagle Road, canal (just north of Plaza Drive) to State Street – Reconstructing the road with concrete pavement, replacing some sidewalk
- Eagle Road will not be widened above the canal
- State Street, Olde Park Place to 2nd Street – Reconstructing the roadway with concrete pavement, replacing/adding sidewalk and streetscaping
- This includes reconfiguring and reconstructing the Eagle Road and State Street intersection
- There will no longer be a left turn from eastbound State Street to southbound Eagle Road
- Drivers will turn left at 2nd Street or Olde Park Place instead
- There will no longer be a left turn from eastbound State Street to southbound Eagle Road
- This includes reconfiguring and reconstructing the Eagle Road and State Street intersection
- Olde Park Place, State St to Aikens Street – Reconstruct and widen the road with asphalt pavement, adding on-street parking and 10-foot sidewalk on both sides
- Aikens Street, Olde Park Place to Eagle Road – Reconstruct the road with asphalt pavement and add 5-foot sidewalk on the north side
- Phase 2 map