July 12, 2023

  • Eagle Road between Plaza and Aikens
    • Veolia will need to shut down Aikens for water change over - after Eagle Fun Days
  • Front of Albertsons - East side of Eagle between Highway 44 and Plaza.
    • Utilities relocating. Concrete ongoing. Will be working on Plaza side. Retaining wall ongoing.
  • Eagle and Plaza Intersection
    • Removing Asphalt. Grading road. Paving anticipated for the week of July 15th.
Share July 12, 2023 on Facebook Share July 12, 2023 on X (formerly Twitter) Share July 12, 2023 on Linkedin Email July 12, 2023 link

This project is substantially complete. 