July 19, 2024
Eagle Road between Plaza and Aikens
- Veolia will need to close Eagle Road at Aikens for a water change over - Anticipated once construction has been completed on Plaza.
Front of Albertsons
- Working on Plaza side. Construction of retaining wall ongoing.
- North side of Plaza started July 19th - One approach at a time will be constructed.
Eagle and Plaza Intersection
- Paving on Eagle complete.
- Signal at Eagle and Plaza was turned on July 18th.
Share July 19, 2024 on Facebook
Share July 19, 2024 on X (formerly Twitter)
Share July 19, 2024 on Linkedin
Email July 19, 2024 link
This project is substantially complete.