July 19, 2024

Eagle Road between Plaza and Aikens

  • Veolia will need to close Eagle Road at Aikens for a water change over - Anticipated once construction has been completed on Plaza.

Front of Albertsons

  • Working on Plaza side. Construction of retaining wall ongoing.
  • North side of Plaza started July 19th - One approach at a time will be constructed.

Eagle and Plaza Intersection

  • Paving on Eagle complete.
  • Signal at Eagle and Plaza was turned on July 18th.


Share July 19, 2024 on Facebook Share July 19, 2024 on X (formerly Twitter) Share July 19, 2024 on Linkedin Email July 19, 2024 link

This project is substantially complete. 