July 25, 2025

Olde Park

Landscape and brick pavers ongoing

Aikens between 2nd and Eagle

Parking lot ongoing. Landscaping ongoing.

Eagle Rd & State Intersection

Started July 7th. Removal of road and signal equipment. Underground work after removals. Veolia starting potentially July 21st. Underground electrical ongoing.


Share July 25, 2025 on Facebook Share July 25, 2025 on Twitter Share July 25, 2025 on Linkedin Email July 25, 2025 link

This project is substantially complete. 