July 26, 2024

Eagle Road between Plaza and Aikens

  • Veolia will need to close Eagle Road at Aikens for water change over. Anticipated August 5th for a week - night work only.

Front of Albertsons

  • Working on Plaza side.
  • Retaining wall construction ongoing.
  • North side of Plaza started July 19th - One approach at a time.

Eagle and Plaza Intersection

  • Paving on Eagle complete.
  • Signal at Eagle and Plaza was turned on July 18th.