Olde Park

  • Landscape and brick pavers ongoing

Aikens between 2nd and Eagle

  • Landscaping ongoing. Parking lot ongoing. Private contractor working at 128 S. Eagle Rd.

Eagle Rd

  • Milling complete. Concrete work ongoing. Paving scheduled for June 26th. Planning on being open for Eagle Fun Days.

The intersection of Eagle and Old State is anticipated to be closed July 7th until the middle of August.