June 28, 2024

Eagle Road between Plaza and Aikens

  • 4-Way Stop at Eagle & Plaza.
  • Bottom lift paving between Plaza & Aikens complete.
  • Veolia will need to shut down Aikens for water change over - waiting until after Eagle Fun Days.

Eagle Road and Plaza Intersection

  • Contractor will be paving in the next three weeks at Eagle & Plaza.
  • Curb & Gutter anticipated to be placed on Eagle and Plaza.
  • Removal of Asphalt July 10th- 12th (Tentative)

Front of Albertsons - East side of Eagle between Highway 44 and Plaza

  • Utilities relocating.
  • Concrete ongoing.
  • Continued work on Plaza side.
  • Boring under canal.

What to expect in the next few weeks

  • Expect heavy congestion
  • Temporary road closure at Plaza Dr.
  • Shifting road patterns
  • Signal turn on expected July 18th
  • Traffic control devices will be removed from Highway 44 & 55 anticipated by July 18th.

Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link

This project is substantially complete. 