Eagle Road between Plaza and Aikens

  • 4-Way Stop at Eagle & Plaza.
  • Bottom lift paving between Plaza & Aikens complete.
  • Veolia will need to shut down Aikens for water change over - waiting until after Eagle Fun Days.

Eagle Road and Plaza Intersection

  • Contractor will be paving in the next three weeks at Eagle & Plaza.
  • Curb & Gutter anticipated to be placed on Eagle and Plaza.
  • Removal of Asphalt July 10th- 12th (Tentative)

Front of Albertsons - East side of Eagle between Highway 44 and Plaza

  • Utilities relocating.
  • Concrete ongoing.
  • Continued work on Plaza side.
  • Boring under canal.

What to expect in the next few weeks

  • Expect heavy congestion
  • Temporary road closure at Plaza Dr.
  • Shifting road patterns
  • Signal turn on expected July 18th
  • Traffic control devices will be removed from Highway 44 & 55 anticipated by July 18th.

Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link