June 6, 2025
Olde Park
- Landscape and brick pavers ongoing.
Aikens between 2nd and Eagle
- Placing silva cells.
- Electrical work ongoing.
- Curb and sidewalk ongoing.
- Asphalt paving was done May 29th.
- Road to be opened June 6th after striping and manhole collaring is complete.
Olde Park To Eagle Rd
- Road closure anticipated May 5th - June 6th.
- Silva cells ongoing.
- Prepping and placing sidewalk crossings.
- Paving was done May 30th.
Starting June 6th, Eagle Road will be closed between Plaza and Old State. Veolia installing water line installation. Excavation and storm drain installation.