June 6, 2025

06 Jun 2025

Olde Park

  • Landscape and brick pavers ongoing.

Aikens between 2nd and Eagle

  • Placing silva cells.
  • Electrical work ongoing.
  • Curb and sidewalk ongoing.
  • Asphalt paving was done May 29th.
  • Road to be opened June 6th after striping and manhole collaring is complete.

Olde Park To Eagle Rd

  • Road closure anticipated May 5th - June 6th.
  • Silva cells ongoing.
  • Prepping and placing sidewalk crossings.
  • Paving was done May 30th.

Starting June 6th, Eagle Road will be closed between Plaza and Old State. Veolia installing water line installation. Excavation and storm drain installation.


Share June 6, 2025 on Facebook Share June 6, 2025 on Twitter Share June 6, 2025 on Linkedin Email June 6, 2025 link
#<Object:0x0000000024979680>