June 7, 2024
- Stage 1 -Eagle Road between Plaza and Aikens
- 4-Way Stop at Eagle & Plaza
- Bottom lift paving between Plaza & Aikens complete
- Veolia will need to shut down Aikens for water change over
- Stage 2 – Front of Albertsons
- East side of Eagle between Highway 44 and Plaza
- Utilities relocating
- Concrete ongoing
- Will be working on Plaza side