March 1, 2024

Phase 1 - Northeast corner of Eagle and Plaza

  • A work zone is in place in the middle of Eagle Road, south of Plaza Drive for Veolia water work.
  • One lane in each direction will remain open (A lane on each side of the work zone).
  • Work will continue on the East side of Eagle Road just North of Plaza Drive.
  • Extruded curb is being removed on Eagle Rd. between Plaza Dr. and Highway 44.
  • Contractor is removing obstructions.
  • Utilities are being relocated.
  • Veolia Permit approved February 26th.
  • Signal work starting March 4th.
  • Flagging is needed at Eagle and Plaza starting Monday, March 4th for utility and signal work.
  • Business access will be maintained.