Eagle Road in front of Albertsons
- Culvert complete
- Retaining wall ongoing
- Curb and gutter getting placed
- Swale ongoing
- Approach at Albertsons ongoing
Veolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am.
Olde Park Place
- Storm Drain and Irrigation complete
- Excavation and backfill ongoing
- Electrical and landscaping ongoing
- Working in State Street working on Silva Cells
Share March 14, 2025 on Facebook
Share March 14, 2025 on X (formerly Twitter)
Share March 14, 2025 on Linkedin
Email March 14, 2025 link
This project is substantially complete.