March 20, 2024
Eagle Road in front of Albertsons
- Culvert complete.
- Retaining wall ongoing.
- Curb and gutter getting placed.
- Swale ongoing.
- Paving anticipated March 21st.
- Concrete median anticipated start March 24th.
Veolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am - Pending Veolia’s contractor schedule.
Olde Park
- Storm drain and irrigation complete.
- Excavation and backfill ongoing.
- Electrical and landscaping ongoing.
- Working in State Street working on Silva Cells.
Aikens between 2nd and Eagle
- Waiting for Eagle Sewer’s contractor to be complete.
Share March 20, 2024 on Facebook
Share March 20, 2024 on Twitter
Share March 20, 2024 on Linkedin
Email March 20, 2024 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends