March 20, 2024

20 Mar 2025

Eagle Road in front of Albertsons

  • Culvert complete.
  • Retaining wall ongoing.
  • Curb and gutter getting placed.
  • Swale ongoing.
  • Paving anticipated March 21st.
  • Concrete median anticipated start March 24th.

Veolia

  • Working at the intersection of Olde Park and State Street - Night work 8pm – 7am - Pending Veolia’s contractor schedule.

Olde Park

  • Storm drain and irrigation complete.
  • Excavation and backfill ongoing.
  • Electrical and landscaping ongoing.
  • Working in State Street working on Silva Cells.

Aikens between 2nd and Eagle

  • Waiting for Eagle Sewer’s contractor to be complete.