March 20, 2024
Eagle Road in front of Albertsons
- Culvert complete.
- Retaining wall ongoing.
- Curb and gutter getting placed.
- Swale ongoing.
- Paving anticipated March 21st.
- Concrete median anticipated start March 24th.
Veolia
- Working at the intersection of Olde Park and State Street - Night work 8pm – 7am - Pending Veolia’s contractor schedule.
Olde Park
- Storm drain and irrigation complete.
- Excavation and backfill ongoing.
- Electrical and landscaping ongoing.
- Working in State Street working on Silva Cells.
Aikens between 2nd and Eagle
- Waiting for Eagle Sewer’s contractor to be complete.
Share March 20, 2024 on Facebook
Share March 20, 2024 on X (formerly Twitter)
Share March 20, 2024 on Linkedin
Email March 20, 2024 link
This project is substantially complete.