March 28, 2025

28 Mar 2025

Eagle Road in front of Albertsons

  • Culvert complete.
  • Retaining wall ongoing.
  • Paving complete.
  • Pavement markings complete.
  • Swale ongoing.
  • Minor items remaining.

Veolia

  • Working at the intersection of Olde Park and State Street
    • Night work 8pm – 7am - TBD
  • Starting on Aikens between 2nd and Eagle.

Olde Park Place

  • Storm Drain and irrigation complete.
  • Excavation and backfill ongoing. Electrical and landscaping ongoing.
  • Working in State Street working on Silva Cells.
  • Placing structural fill.
  • Curb and gutter starting first week of April.

Aikens between 2nd and Eagle

  • Eagle Sewer is complete.
  • Sub grading road.