March 28, 2025
Eagle Road in front of Albertsons
- Culvert complete.
- Retaining wall ongoing.
- Paving complete.
- Pavement markings complete.
- Swale ongoing.
- Minor items remaining.
Veolia
- Working at the intersection of Olde Park and State Street
- Night work 8pm – 7am - TBD
- Starting on Aikens between 2nd and Eagle.
Olde Park Place
- Storm Drain and irrigation complete.
- Excavation and backfill ongoing. Electrical and landscaping ongoing.
- Working in State Street working on Silva Cells.
- Placing structural fill.
- Curb and gutter starting first week of April.
Aikens between 2nd and Eagle
- Eagle Sewer is complete.
- Sub grading road.
Share March 28, 2025 on Facebook
Share March 28, 2025 on X (formerly Twitter)
Share March 28, 2025 on Linkedin
Email March 28, 2025 link
This project is substantially complete.