March 28, 2025
Eagle Road in front of Albertsons
- Culvert complete.
- Retaining wall ongoing.
- Paving complete.
- Pavement markings complete.
- Swale ongoing.
- Minor items remaining.
Veolia
- Working at the intersection of Olde Park and State Street
- Night work 8pm – 7am - TBD
- Starting on Aikens between 2nd and Eagle.
Olde Park Place
- Storm Drain and irrigation complete.
- Excavation and backfill ongoing. Electrical and landscaping ongoing.
- Working in State Street working on Silva Cells.
- Placing structural fill.
- Curb and gutter starting first week of April.
Aikens between 2nd and Eagle
- Eagle Sewer is complete.
- Sub grading road.
Share March 28, 2025 on Facebook
Share March 28, 2025 on Twitter
Share March 28, 2025 on Linkedin
Email March 28, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends