March 29, 2024

  • Phase 1 - Northeast corner of Eagle and Plaza
    • Removal of obstructions and tree removal ongoing.
    • Utilities relocating.
    • Signal work ongoing.
    • Landscaping wall ongoing.
  • Veolia
    • Locating utilities.
    • Boring complete.
    • Crossing Eagle complete.
    • Stopped at Intersection of Plaza and Eagle.
  • Plaza and Eagle Road Closure - Closed from April 1st – 15th.
    • Veolia tie in water in middle of intersection then proceeding down Plaza.
    • Signal work crossing Eagle Road.
    • Irrigation and conduits crossing Eagle during closure.
  • Eagle Road Closure - April 15th – April 30th.
    • Veolia water line to Aikens.