March 29, 2024

  • Phase 1 - Northeast corner of Eagle and Plaza
    • Removal of obstructions and tree removal ongoing.
    • Utilities relocating.
    • Signal work ongoing.
    • Landscaping wall ongoing.
  • Veolia
    • Locating utilities.
    • Boring complete.
    • Crossing Eagle complete.
    • Stopped at Intersection of Plaza and Eagle.
  • Plaza and Eagle Road Closure - Closed from April 1st – 15th.
    • Veolia tie in water in middle of intersection then proceeding down Plaza.
    • Signal work crossing Eagle Road.
    • Irrigation and conduits crossing Eagle during closure.
  • Eagle Road Closure - April 15th – April 30th.
    • Veolia water line to Aikens.
Share March 29, 2024 on Facebook Share March 29, 2024 on Twitter Share March 29, 2024 on Linkedin Email March 29, 2024 link

This project is substantially complete. 