March 29, 2024
- Phase 1 - Northeast corner of Eagle and Plaza
- Removal of obstructions and tree removal ongoing.
- Utilities relocating.
- Signal work ongoing.
- Landscaping wall ongoing.
- Veolia
- Locating utilities.
- Boring complete.
- Crossing Eagle complete.
- Stopped at Intersection of Plaza and Eagle.
- Plaza and Eagle Road Closure - Closed from April 1st – 15th.
- Veolia tie in water in middle of intersection then proceeding down Plaza.
- Signal work crossing Eagle Road.
- Irrigation and conduits crossing Eagle during closure.
- Eagle Road Closure - April 15th – April 30th.
- Veolia water line to Aikens.
Share March 29, 2024 on Facebook
Share March 29, 2024 on X (formerly Twitter)
Share March 29, 2024 on Linkedin
Email March 29, 2024 link
This project is substantially complete.