March 6, 2025

Eagle Road in front of Albertsons

  • Culvert complete.
  • Retaining wall installed after the backfill complete.
  • Curb and gutter anticipated starting March 10th.
  • Swale ongoing.
  • Approach at Albertsons ongoing.

Veolia

  • Working at the intersection of Olde Park and State Street.
  • Night work 8pm – 7am.

Olde Park

  • Storm drain and irrigation ongoing.
  • Sub grading after underground is work complete.
  • Electrical and landscaping underground will be after the irrigation line is installed.
  • Working on State Street to install silva cells.
Share March 6, 2025 on Facebook Share March 6, 2025 on X (formerly Twitter) Share March 6, 2025 on Linkedin Email March 6, 2025 link

This project is substantially complete. 