March 8, 2024

  • Phase 1 - Northeast corner of Eagle and Plaza
  • Removal of obstructions and tree removal ongoing.
  • Utilities relocating.
  • Signal work at Plaza started March 3rd.
  • Placing bases for new signal poles.
  • Veolia Permit approved February 26th.
  • Locating utilities.
  • Removing extruded curb between Eagle and Highway 44.
  • Potholing and boring started the week of March 4th.
Share March 8, 2024 on Facebook Share March 8, 2024 on X (formerly Twitter) Share March 8, 2024 on Linkedin Email March 8, 2024 link

This project is substantially complete. 