March 8, 2024
- Phase 1 - Northeast corner of Eagle and Plaza
- Removal of obstructions and tree removal ongoing.
- Utilities relocating.
- Signal work at Plaza started March 3rd.
- Placing bases for new signal poles.
- Veolia Permit approved February 26th.
- Locating utilities.
- Removing extruded curb between Eagle and Highway 44.
- Potholing and boring started the week of March 4th.