May 1, 2025

Olde Park

  • Landscape ongoing

Aikens between 2nd and Eagle

  • Placing Silva Cells
  • Placing ¾” aggregate for road base
  • Electrical work ongoing
  • Curb anticipated week of May 5th

Olde Park To Eagle Rd

  • Road closure anticipated May 5th – May 30th
  • Veolia installing water
  • Silva cells ongoing
  • Prepping and placing sidewalk crossings
Share May 1, 2025 on Facebook Share May 1, 2025 on Twitter Share May 1, 2025 on Linkedin Email May 1, 2025 link

This project is substantially complete. 