May 1, 2025
Olde Park
- Landscape ongoing
Aikens between 2nd and Eagle
- Placing Silva Cells
- Placing ¾” aggregate for road base
- Electrical work ongoing
- Curb anticipated week of May 5th
Olde Park To Eagle Rd
- Road closure anticipated May 5th – May 30th
- Veolia installing water
- Silva cells ongoing
- Prepping and placing sidewalk crossings
Share May 1, 2025 on Facebook
Share May 1, 2025 on X (formerly Twitter)
Share May 1, 2025 on Linkedin
Email May 1, 2025 link
This project is substantially complete.