May 16, 2024
- Eagle Road Closure ended April 30th
- 4-Way Stop at Eagle & Plaza. Bottom lift paving between Plaza & Aikens complete. Sidewalk between Plaza and Aikens ongoing. Signal Poles placed. Landscaping wall ongoing.
- Front of Albertsons anticipated starting May 16th - east side of Eagle between Highway 44 and Plaza.
- Clearing and grubbing berm.
- Concrete ongoing.
Share May 16, 2024 on Facebook
Share May 16, 2024 on Twitter
Share May 16, 2024 on Linkedin
Email May 16, 2024 link
This project is substantially complete.